CCLIENT |
|
|
PROJECT MANAGER |
|
|
CONTRACTOR |
|
RN Infra Pvt.Ltd
|
PROJECT NAME |
- |
|
|
|
|
|
|
|
|
A |
22-09-2020 |
For review & Approval |
Mr.Nitin Gupta |
|
|
|
Rev. No. |
Date |
Description |
Prepared by |
Checked by |
Reviewed by |
Approved by |
This document is exclusive property of Infinity
Interiors. It is to be used only for the purpose which it is lent and must
not be copied or used in any way detrimental to the interest of this company
and subject to return on demand. |
TABLE OF CONTENTS
Sr.No |
Description |
Page No |
1 |
INTRODUCTION |
3 |
2 |
PURPOSE |
3 |
3 |
SCOPE |
3 |
4 |
REFRENCE,STANDARDS
& SPECIFICATION |
3 |
5 |
RESPONSIBILITY |
4 |
6 |
DEFINITIONS /
ABBREVIATION |
4 |
7 |
MAJOR RESOURCES
DEPLOYED |
4 |
8 |
EQUIPMENTS
& MATERIALS |
5 |
9 |
PROCEDURE |
5 |
10 |
PERMIT TO WORK |
6 |
11 |
PREPRATION |
6 |
12 |
HEALTH ,SAFETY
& ENVIRONMENT |
6 |
13 |
TOOLS &
EQUIPMENT |
7 |
14 |
ATTACHEMENT |
7 |
INTRODUCTION -
This Method Statement
describes the methodology to execute all activities for Painting Work Preparation
with in Flat area includes– Wall, Floor, and associated works.
The objective of
this method statement is to clearly understand the job for the execution of the
job along with safety precautions, which are necessary to avoid any kind of
injuries / accidents to personnel or any damage to any equipment or property.
We have prepared this method statement for the situation clearly stated that
how Infinity Interiors will perform the Tiles works in the tower area.
2.
PURPOSE
The purpose of the water proofing and all other related works shall be
executed as the part of Godrej nature plus Project. This method statement describes
the construction procedure to be followed at the site.
All activities within the project scope of work are carried
out safely by Infinity Interiors in strict compliance with HBOCW act.
3.
SCOPE
The scope of this
method statement includes but not limited to the following activities;
·
Material Handling
·
Scaffoldings
4.
REFERENCES, STANDARDS & SPECIFICATIONS - :
Project
specifications and BOQ
Project Quality Plan
Project HSE Plan
Quality Control Procedures
Contract Drawings and Specifications
Manufacturers’ brochures/ literature and other details as a part of this method
statement.
All work shall be executed in compliance with the requirements of Project
Specifications & Emergency Response Procedures, and other applicable
standards
Approved drawings for constructions with code A and B for works, materials
approval submitted/ to be submitted as applicable and related approved method
statement & ITP’s (Inspection and Test Plan).
5. RESPONSIBILITY:
a. Performing authority/Permit Holder shall be working time available at
site and responsible for managing all job, machinery and labor for related job.
b.
The QA/QC engineer/Inspector shall be
responsible for ensuring the quality of work as per the specifications.
c.
Engineer/Supervisor shall be full
working time available at site and responsible to execute and supervise all the
works according to this Method Statement.
d.
The safety Supervisor shall be full
working time available at site and responsible to ensure work being executed in
safe manner.
e.
Project Manager shall be responsible for
whole work activity.
6.
DEFINITIONS / ABBREVIATION
COMPANY : Client Name
CONTRACTOR : RN INFRA Pvt Ltd
HSE : HEALTH, SAFETY AND
ENVIRONMENT
PTW :
PERMIT TO WORK.
TBT :
TOOL BOX TALK
QA/QC : QUALITY ASSURANCE AND QUALITY
CONTROL
HIRA :
HAZARD IDENTIFICATION & RISK ASSESSMENT
7.
MAJOR RESOURCES DEPLOYED:
§ Water
§ Paint
§ Primer
§ Brush
§ Roller
§ Sand paper
§ Rough cloth
§ Drip tray
§ Drill machine
8.1 Equipment
& Materials
The equipment & materials involved in above mentioned works are
mentioned below:
·
Paint Brush
·
Paint Roller
·
Spray Paint
·
Spatula
·
Scraper
·
Trowel
·
Sand Paper
·
Thinner
·
Extension Ladder
·
Approved brand Paint
8.2 Man power
The personnel involved in these operations mentioned as below:
Ø
Safety Supervisor.
Ø
Site Engineer/
Ø
QA/QC Engineer
Ø
Foreman / Charge hand
Ø
Painter
Ø
Helpers
9 .0 PROCEDURE
Apply paint by brush, roller, spray, or other acceptable
practice in accordance with the manufacturer’s directions. Use brushes best
suited area for the type of material being applied. Except as otherwise
specified, apply a prime coat to material which is required to be painted or
finished. Apply the first-coat material to surfaces that
have been cleaned, pre-treated or otherwise prepared for painting as soon as
practicable after preparation and before subsequent surface deterioration. Number
of coats and paint film thickness required is the same regardless of the
application method. Sand between each enamel and varnish coat application with
fine sandpaper or rub surfaces with pumice stone where required to produce an
even, smooth surface in accordance with the paint manufacturer’s directions.
10.0 PERMIT TO WORK
Work permits shall be obtained from GPL (if
necessary) it will be followed for all activities. All safety precautionary
measures outlined in respective work permits will be fully adhered.
10.1 INDUCTION
Ø All employees including subcontractor’s personnel,
on the project site will be inducted in Safety related matters by Infinity
prior to enter to the work site.
Ø The workforce will be communicated /briefed for
HAZARDs and minor injury associated during work Tower area.
Ø Performing authority will conduct TBT and brief the hazards and control measures involved in work before commencement.
11.0 PREPARATION
Ø Material Shifting
Ø Chemical Mixing (with
MSDS submitted)
12.0 HEALTH,
SAFETY & ENVIRONMENT
Ø All workforces
shall attend induction training provided by Infinity safety person.
Ø All personnel
involving in various stages of construction will attend the “TBT “(Tool box
TALK)” conducted prior to start day's activity on daily basis and will be
ensured to make them aware about potential hazards involved within the work
area & relevant safety measures to be taken.
Ø Competent work force will be deployed for the job. They will be trained for safety requirements and procedures of the job and risks involved in the job.
Ø First Aid Facility will be available at site.
Ø All personnel will be used to necessary PPE’s.
Ø Adequate drinking
water facility and amenities will be provided.
Ø Adequate
safety sign boards will be placed all around the work & site area.
Ø List
of emergency contact telephone numbers will be made available to all Key
personnel associated with this work for all the time.
Ø All
personnel involved in works shall be aware of Safety requirements of the
project and the site shall be kept clean and tidy conditions all the time.
Ø All
access / exit points to work areas shall be maintained free from obstacles,
materials and equipment.
Ø Safety supervision will be made available
continuously and will monitor the work activities.
Ø Portable
fire extinguishers (ABC 6 Kg) shall be provided at the site wherever necessary.
Ø Risk
Assessment (HIRA) will be performed to assess the hazards involved and control
measures to be taken prior to start of activity and submitted for Company
review. All control measures will be ensured according to HIRA.
Ø All
the equipment/machineries for the works will be kept at safe locations.
Ø All workers Mandatory
nose mask and social distancing due to Covid -19.
13 .0 TOOLS AND
EQUIPMENT
Tape Measure
Framing Square
Marker
Rubber Gloves
Buckets
Rubber Mallet
Sponges
Chalk Line
Carpenter’s Triangle
Gloves
Safety Glasses
Paint
Primer
14.0 ATTACHMENTS
Ø HIRA: (RNPL-HSE-HIRA-00)
0 Comments: