    CLIENT

 

     PROJECT MANAGER


     CONTRACTOR

 

 


 

     PROJECT NAME 

-

 

                                                                                  TABLE OF CONTENTS 

Sr.No

Description

Page No

1

INTRODUCTION

3

2

PURPOSE

3

3

SCOPE

3

4

REFENCES, STANDARED & SPECIFICATIONS

3

5

RESPONSIBILITY

4

6

DEFINITIONS / ABBREVIATION

4

7

MAJOR RESOURCES DEPLOYED

4

8

EQUIPMENT & MATERIAL

5

9

PROCEDURE

5 to 6

10

PERMIT TO WORK

7

11

PREPARATION

7

12

HEALTH, SAFETY AND ENVIRONMENT

7

13

TOOLS & EQUIPMENT

8

14

ATTACHMENTS

8


                Introduction-

This Method Statement describes the methodology to execute all activities for Stone Work Preparation with in Flat area .

The objective of this method statement is to clearly understand the job for the execution of the job along with safety precautions, which are necessary to avoid any kind of injuries / accidents to personnel or any damage to any equipment or property. We have prepared this method statement for the situation clearly stated that how Infinity Interiors will perform the Tiles works in the tower area.

2.         PURPOSE

The purpose of the water proofing and all other related works shall be executed as the part of Godrej nature plus Project. This method statement describes the construction procedure to be followed at the site.

All activities within the project scope of work are carried out safely by Infinity Interiors in strict compliance with HBOCW act.

3.         SCOPE

The scope of this method statement includes but not limited to the following activities;

·           Material Handling 

·           Level Checking & Cleaning

·           Plastering

·           Cutting Fixing

4.         REFERENCES, STANDARDS & SPECIFICATIONS - :

Project specifications and BOQ
Project Quality Plan
Project HSE Plan
Quality Control Procedures
Contract Drawings and Specifications
Manufacturers’ brochures/ literature and other details as a part of this method statement.
All work shall be executed in compliance with the requirements of Project Specifications & Emergency Response Procedures, and other applicable standards
Approved drawings for constructions with code A and B for works, materials approval submitted/ to be submitted as applicable and related approved method statement & ITP’s (Inspection and Test Plan).
 

5.         RESPONSIBILITY:

a.       Performing authority/Permit Holder shall be full time available at site and responsible for managing all job, machinery and labor for related job.

b.      The QA/QC engineer/Inspector shall be responsible for ensuring the quality of work as per the specifications.

c.       Engineer/Supervisor shall be full time available at site and responsible to execute and supervise all the works according to this Method Statement.

d.      The safety Supervisor shall be full time available at site and responsible to ensure work being executed in safe manner.

e.       Project Manager shall be responsible for executing the work in safer manner.

6.         DEFINITIONS / ABBREVIATION

COMPANY          :   

 

CONTRACTOR  :   


HSE                      :  HEALTH, SAFETY AND ENVIRONMENT

 

PTW                     : PERMIT TO WORK.

 

 TBT                    :   TOOL BOX TALK

 

QA/QC              : QUALITY ASSURANCE AND QUALITY CONTROL

 

HIRA               : HAZARD INDENTIFICATION & RISK ASSESSMENT 

 

7.         MAJOR RESOURCES DEPLOYED:

§  Laser Radiation level Machine

§  Sand

§  Cement

§  Water 

8.1 Equipment & Materials

 The equipment & materials involved in above mentioned works are mentioned below:

 Ã˜  Laser Radiation Level Machine

Ø  Marble Drill Machine

Ø  7” Grinding Machine

Ø  4” Grinding Machine

Ø  Pick Up

 8.2 Man power

The personnel involved in these operations mentioned as below:

Ø  Safety Supervisor.

Ø  Site Engineer/

Ø  QA/QC Engineer

Ø  Foreman / Charge hand

Ø  Mason

Ø  Helpers

9        PROCEDURE

                 9.1 Pre-Installation:

Site Condition Checking And Setting Out -

Ø  GPL team  shall check site condition to ensure readiness for tile fixing. Main contractor shall sign off clearance to lay stone for each floor separately.

Ø  Store approved marble tiles near each work area.

Ø  All other work must be finalized prior to marble installation.

Ø  Check the surfaces indicated to receive stone flooring for compliance with requirements.

Ø  Clean concrete substrates to remove dirt, dust, debris and loose particles that could affect mortar bond.

Ø  Clean dirty or stained stone surface using clean water.

Ø  Dry-lay marble designated to each level. Submit inspection request for marble approval prior to final fixing at required level.

Ø  Apply water proof material to back of marble in two coats. If applicable. 

9.2 Preparation Area

Ø  GPL Team shall check site condition to ensure readiness for tile fixing.

Ø  Approved marble tiles will be handling near each working area.

Ø  Check the layout shop drawings related grid lines & levels are given.

Ø  Clean concrete substrates by removing dirt, dust, debris and loose particles that could affect mortar bond.

Ø  Clean dirty or stained stone surface using clean water.

Ø  Dry-lay marble designated to each level.

Ø  MEP clearance or any other work.

Ø  Mortar/ bonding material to be ready at required area.

 

9.3 Grouting Of Stonework Joints

Ø  Check and ensure that the mortar bed has set. Clean off all loose toppings or any substances that may reduce or inhibited the grout to the stonework joints.

Ø  Add 10 Kg of approved grout product fine grain to 2.1 – 2.3 liters of clean water stir until a homogeneous paste. Leave to rest for 2 to 3 minutes and remix before.

Ø  Apply the grout with a rubber trowel to fill the joints completely.

Ø  Wait for 10-20 minutes and clean off excess grout slightly damped sponge.

Ø  For stone flooring; allow the grout to set for at least 24 hours before allowing foot trafficking.

 9.4 Temporary Protection

Ø  Floors inspected and approved shall be protected as follows:

Ø  Clean marble with Wiper using clean water

Ø  Apply Polypropylene board sheets to marble surface for foot traffic protection; more than the foot traffic, the main contractor shall be responsible for the protection.

 9.5 Final Polishing:

Ø  All floors shall be polished to achieve approved sample / Mockup.

Ø  Then no further protection will be applied.

9.6 Control Joints:

Control joints, as shown on drawing will be applied around floor perimeter at walls & columns, as follows:

 1.        As per the drawing indication

2.       Application as per Manufacturer’s instruction

10 . PERMIT TO WORK

Work permits shall be obtained from GPL (if necessary) it will be followed for all activities. All safety precautionary measures outlined in respective work permits will be fully adhered.

10.1  INDUCTION

Ø All employees including subcontractor’s personnel, on the project site will be inducted in Safety related      matters by Infinity prior to enter to the work site.

Ø  The workforce will be communicated /briefed for any types HAZARDs & Minor Injury associated during work Tower area.

Ø  Performing authority will conduct TBT and brief the hazards and control measures involved in work before commencement.

11 .0 PREPARATION

Ø   Material Shifting

Ø  Chemical Mixing

12.0 HEALTH, SAFETY & ENVIRONMENT

Ø  All workforces shall attend induction training provided by Infinity.

Ø  All personnel involving in various stages of construction will attend the “TBT “(Tool box TALK Meeting)” conducted prior to start day's activity on daily basis and will be ensured to make them aware about potential hazards involved within the work area & relevant safety measures to be taken.

Ø  Competent work force will be deployed for the job. They will be trained for safety requirements and procedures of the job and risks involved in the job.

Ø  First aid facility will be available during work.

Ø  All personnel will be used necessary PPEs.

Ø  Adequate drinking water facility and amenities will be provided.

Ø  Adequate safety sign boards will be placed all around the work area.

Ø  List of emergency contact telephone numbers will be made available to all Key personnel associated with this work for all the time.

Ø  All personnel involved in works shall be aware of Safety requirements of the project and the site shall be kept clean and tidy conditions all the time.

Ø  All access / exit points to work areas shall be maintained free from obstacles, materials and equipment.

Ø   Safety supervision will be made available continuously and will monitor the activities.

Ø  Portable fire extinguishers (ABC 6 Kg) shall be provided at the site wherever necessary.

Ø  Risk Assessment (HIRA) will be performed to assess the hazards involved and control measures to be taken prior to start of activity and submitted for Company review. All control measures will be ensured according to HIRA.

Ø  All the equipment/machineries for the works will be kept at safe locations.

Ø  All workers Mandatory nose mask and social distancing due to Covid -19 .

13.0 TOOLS AND EQUIPMENT
Tape Measure
Framing Square
Marker
Rubber Gloves
Screed Board
Buckets
Rubber Mallet
Sponges
Chalk Line
Carpenter’s Triangle
Gloves
Safety Glasses
One-bagger mixer
Mechanical mixer for dry mixing
Scrapper

14.0 ATTACHMENTS

Ø  HIRA : (IIPL-HSE-HIRA-00)

 