Headlines
Loading...

 

 

v CLIENT

 Godrej Properties Limited 

   PROJECT MANAGER

Godrej Properties Limited 

   CONTRACTOR

 

 

 

 

    PROJECT NAME 

-

 Godrej Nature +

  

 

 

 

 

 

 

 

 

A

22-09-2020

For review & Approval

 Mr.Nitin Gupta

 Mr.Rahul  


      

Rev. No.

Date

Description

Prepared by

Checked by

Reviewed by

Approved by

This document is exclusive property of ....... It is to be used only for the purpose which it is lent and must not be copied or used in any way detrimental to the interest of this company and subject to return on demand.

                                                                   TABLE OF CONTENTS - :  

Sr.No

Description

Page No

1

INTRODUCTION

3

2

PURPOSE

3

3

SCOPE

3

4

REFRENCE,STANDARDS & SPECIFICATION

3

5

RESPONSIBILITY

4

6

DEFINITIONS / ABBREVIATION

4

7

MAJOR RESOURCES DEPLOYED

4

8

EQUIPMENTS & MATERIALS

5

9

PROCEDURE

5

10

PERMIT TO WORK

6

11

PREPRATION

6

12

HEALTH ,SAFETY & ENVIRONMENT

6

13

TOOLS & EQUIPMENT

7

14

ATTACHEMENT

7


 
  INTRODUCTION

This Method Statement describes the methodology to execute all activities for Painting Work Preparation with in Flat area includes– Wall, Floor, and associated works.

The objective of this method statement is to clearly understand the job for the execution of the job along with safety precautions, which are necessary to avoid any kind of injuries / accidents to personnel or any damage to any equipment or property. We have prepared this method statement for the situation clearly stated that how Infinity Interiors will perform the Tiles works in the tower area.

2.         PURPOSE

The purpose of the water proofing and all other related works shall be executed as the part of Godrej nature plus Project. This method statement describes the construction procedure to be followed at the site.

All activities within the project scope of work are carried out safely by Infinity Interiors in strict compliance with HBOCW act. 

3.         SCOPE

The scope of this method statement includes but not limited to the following activities;

·           Material Handling 

·           Scaffoldings

4.         REFERENCES, STANDARDS & SPECIFICATIONS - :

Project specifications and BOQ
Project Quality Plan
Project HSE Plan
Quality Control Procedures
Contract Drawings and Specifications
Manufacturers’ brochures/ literature and other details as a part of this method statement.
All work shall be executed in compliance with the requirements of Project Specifications & Emergency Response Procedures, and other applicable standards
Approved drawings for constructions with code A and B for works, materials approval submitted/ to be submitted as applicable and related approved method statement & ITP’s (Inspection and Test Plan).

5.         RESPONSIBILITY:

a.       Performing authority/Permit Holder shall be working time available at site and responsible for managing all job, machinery and labor for related job.

b.      The QA/QC engineer/Inspector shall be responsible for ensuring the quality of work as per the specifications.

c.       Engineer/Supervisor shall be full working time available at site and responsible to execute and supervise all the works according to this Method Statement.

d.      The safety Supervisor shall be full working time available at site and responsible to ensure work being executed in safe manner.

e.       Project Manager shall be responsible for whole work activity.

 

6.         DEFINITIONS / ABBREVIATION

 

COMPANY          :   

 

CONTRACTOR  : 

 

HSE                      :  HEALTH, SAFETY AND ENVIRONMENT

 

PTW                     : PERMIT TO WORK.

 

 TBT                    :   TOOL BOX TALK

 

QA/QC              : QUALITY ASSURANCE AND QUALITY CONTROL

 

HIRA               : HAZARD IDENTIFICATION & RISK ASSESSMENT

 

7.         MAJOR RESOURCES DEPLOYED:

§  Water

§  Paint

§   Primer

§  Brush

§  Roller

§  Sand paper

§  Rough cloth

§  Drip tray

§  Drill machine

 

8.1 Equipment & Materials

The equipment & materials involved in above mentioned works are mentioned below:

·         Paint Brush

·         Paint Roller

·         Spray Paint

·         Spatula

·         Scraper

·         Trowel

·         Sand Paper

·         Thinner

·         Extension Ladder

·         Approved brand Paint

8.2 Man power

The personnel involved in these operations mentioned as below:

Ø  Safety Supervisor.

Ø  Site Engineer/

Ø  QA/QC Engineer

Ø  Foreman / Charge hand

Ø  Painter

Ø  Helpers

9 .0 PROCEDURE 

Apply paint by brush, roller, spray, or other acceptable practice in accordance with the manufacturer’s directions. Use brushes best suited area for the type of material being applied. Except as otherwise specified, apply a prime coat to material which is required to be painted or finished. Apply the first-coat material to surfaces that have been cleaned, pre-treated or otherwise prepared for painting as soon as practicable after preparation and before subsequent surface deterioration. Number of coats and paint film thickness required is the same regardless of the application method. Sand between each enamel and varnish coat application with fine sandpaper or rub surfaces with pumice stone where required to produce an even, smooth surface in accordance with the paint manufacturer’s directions.

10.0  PERMIT TO WORK

Work permits shall be obtained from GPL (if necessary) it will be followed for all activities. All safety precautionary measures outlined in respective work permits will be fully adhered.

10.1 INDUCTION

Ø All employees including subcontractor’s personnel, on the project site will be inducted in Safety related matters by Infinity prior to enter to the work site.

Ø  The workforce will be communicated /briefed for HAZARDs and minor injury associated during work Tower area.

Ø  Performing authority will conduct TBT and brief the hazards and control measures involved in work before commencement.

PREPARATION

Ø   Material Shifting

Ø  Chemical Mixing (with MSDS submitted)

 HEALTH, SAFETY & ENVIRONMENT

Ø  All workforces shall attend induction training provided by Infinity safety person.

Ø  All personnel involving in various stages of construction will attend the “TBT “(Tool box TALK)” conducted prior to start day's activity on daily basis and will be ensured to make them aware about potential hazards involved within the work area & relevant safety measures to be taken.

Ø  Competent work force will be deployed for the job. They will be trained for safety requirements and procedures of the job and risks involved in the job.

Ø  First Aid Facility will be available at site.

Ø  All personnel will be used to necessary PPE’s.

Ø  Adequate drinking water facility and amenities will be provided.

Ø  Adequate safety sign boards will be placed all around the work & site area.

Ø  List of emergency contact telephone numbers will be made available to all Key personnel associated with this work for all the time.

Ø  All personnel involved in works shall be aware of Safety requirements of the project and the site shall be kept clean and tidy conditions all the time.

Ø  All access / exit points to work areas shall be maintained free from obstacles, materials and equipment.

Ø   Safety supervision will be made available continuously and will monitor the work activities.

Ø  Portable fire extinguishers (ABC 6 Kg) shall be provided at the site wherever necessary.

Ø  Risk Assessment (HIRA) will be performed to assess the hazards involved and control measures to be taken prior to start of activity and submitted for Company review. All control measures will be ensured according to HIRA.

Ø  All the equipment/machineries for the works will be kept at safe locations.

Ø  All workers Mandatory nose mask and social distancing due to Covid -19.

 TOOLS AND EQUIPMENT

Tape Measure
Framing Square
Marker
Rubber Gloves
Buckets
Rubber Mallet
Sponges
Chalk Line
Carpenter’s Triangle
Gloves
Safety Glasses
Paint

Primer 

   ATTACHMENTS

Ø  HIRA: (RNPL-HSE-HIRA-00)

 

Rahul “Nitin”Gupta (BE Civil Engineering ,PMP,MBA Project Management ) is Project Director of this organization he have 8 years of experience in construction industry .He is experts in Site execution, planning , billing department ,Technical advisor .

0 Comments: