Headlines
Loading...

CONSTRUCTION

4.1    Placement of Sub-base Courses

 

4.1.1 The granular sub-base (GSB) material shall be placed and spread evenly on the prepared formation to a compacted thickness as shown on the drawings or as directed by the COMPANY. The preparation of the formation shall be completed at least 200mm ahead of the placing of sub-base material. The maximum compacted thickness of any one layer shall not exceed 150mm. When the specified compacted thickness

 

 


 

 

exceeds 150mm the material shall be laid in two or more approximately equal layers, each not exceeding 150mm.

4.1.2 The sub-base materials shall be thoroughly compacted with suitable and adequate compaction equipment approved by COMPANY.

4.1.3 Rolling operation shall be from the outer edge towards the centre and proceed gradually in a longitudinal direction except on super elevated curves where rolling shall proceed from the low side and move towards the high side.

 

4.1.4 The finish sub-base level shall not vary more than +/-20mm from the grade or level shown on the drawings.

4.2    Placement of Road Base

 

4.2.1 All work on the portion of the granular sub-base on which the wet mix macadam base is to be laid shall be properly shaped and compacted at least 180mm ahead of the placing of the road base material.

 

4.2.2 All materials shall be placed and spread evenly over the full width of the required layer by spreader or grader as approved by COMPANY. Compaction to the thickness as shown on the drawings, or as directed by COMPANY, shall be completed as soon as possible after the material has been spread. The maximum compacted thickness of any one layer shall not exceed 150mm. When the specified compacted thickness exceeds 150mm the material shall be laid in two or more approximately equal layers each not exceeds 150mm.

 

4.2.3 Each layer shall be thoroughly compacted with suitable compacted. Rolling operations shall begin along the edges and progress towards the centre gradually in a longitudinal direction except on super-elevated curves where rolling shall proceed from the low side and progress towards the high side.

 

4.2.4   The surface of the layer shall, on compaction, be well closed, free from movement from compacted planes, ridges, cracks or loose material. All loose, segregated or otherwise defective areas shall be made good to the full thickness of the layer and re-compacted.

 

4.2.5 The finished wet mix macadam base surface base surface shall not vary in level more than +10mm, or -15mm from the levels shown on the drawings. Surface irregularities shall be measured; both longitudinally and transversely, by a 3m long straightedge placed either parallel with, or right angle to, the centreline of the road. The maximum deviation of the road base surface shall be 8mm. Where irregularities in excess of 8mm occur, the surface shall be rectified by scarifying, reshaping with material added or removed as necessary.

 

4.2.6 After placing but before compacted of any layer of road base commences a partial width of the shoulder, not less than 450mm wide, shall be constructed adjacent to the road base to act as a haunch to the edges of the layer. This material shall be compacted along with the road base.

 

4.2.7 The wet mix macadam base material shall be maintained at the correct moisture content necessary for proper compaction by drying out as required.

4.2.8 When a base is spread adjacent to concrete curbs or gutter sections, extreme care shall be exercised so as not to damage the kerbs or gutters. Any damaged curbs or gutters shall be removed and replaced at the CONTRACTOR’s own expense.


4.2.9 The wet mix macadam surface shall be well brushed with mechanical sweepers or stiff brush and swept clean of all loose materials, dust and debris in preparation to receive the tack coat and premix. The brushing and sweeping shall be done at least 2 hours before premix is laid. Once the surface is brushed and swept, no traffic shall be allowed to use that portion of the road unit the surfacing of the portion is completed.

4.3    Preparation of Formation to Receive Road Pavement

 

4.3.1 CONTRACTOR shall ensure sub-grade is at required elevation.

 

4.3.2 The subgrade material in the road formation shall be compacted to a 95% maximum dry density over the upper 600mm layer of the formation.

 

4.3.3 Soft sport and unsuitable materials encountered in the pavement subgrade shall be removed and backfilled with approved suitable material and compacted by not less than four (4) passes of a smooth wheeled roller weighting not less than 10 tonne or an equivalent vibratory roller. The formation shall be checked and the final trimmed surface shall be rolled by one pass of a smooth wheeled roller of not less than 5 tonne.

4.3.4 When sufficient moisture content exists, water and thoroughly mix the subgrade until optimum moisture content is obtained. When excess moisture content exists, rework and aerate the sub-grade until optimum moisture content is obtained.

4.3.5 Before final rolling, shape the entire section, add additional subsoil as required, and compact the subgrades, elevation and cross sections as indicated on the drawings. All points of finished subgrade section shall be within 25mm of the required section.

4.4    Bituminous Surfacing

 

4.4.1 Pavement Section

 

a.    This consists of, from the wet mix macadam road base and upwards:

 

        Prime Coat

 

        Bituminous Base Course

 

        Tack Coat

 

        Dense Bituminous Wearing Course

 

4.4.2 Prime Coat Application

 

a.    The CONTRACTOR shall apply the prime coat on the completed portion of the road base as soon as practicable. However, CONTRACTOR shall not apply the tack coat if the moisture content in the top 50mm of the wet mix macadam road base exceeds the higher of either, the average of the optimum moisture content as determined by the standard compaction test and the absorption of the plus 5mm sieve fraction or two third of the optimum moisture contents as determined by the standard compaction test.

 

b.     The Surface of the road base shall be cleaned immediately and shall be free of all loose material, foreign matter and standing water, prior to the application of the prime coat. The bituminous material

 

shall be applied by means of a distributor at the rates of 0.435 litre/m2 and within the temperature range requirement by IS-73, IS-217, IS-3117 and IS-8887.

4.4.3 Tack coat Application

 

a.    The surface of the Bitumen Macadam Base course shall be cleaned immediately prior to the application of the tack coat.

 

b.    The bitumen material shall be applied by means of a distributor at the rates directed by COMPANY, but shall not be less than 0.326 litre/m2 within the temperature range requirement by IS-73, IS-217, IS-3117 and IS-8887.

 

c.    The Sprayed surface shall be allowed to cure for at least 8 hours prior to any surfacing being laid.

 

4.4.4 Transporting

 

a.    The premix shall be expeditiously transported from manufacturing plant to the site of the works in clean vehicles adequately covered by canvas or tarpaulins to minimize the loose of temperature and protect the premix from rain, dust or spilling on top the road surface. The temperature of the work mixed material as delivered to the work site should not be less than 1040C, at the time of rolling not less than 970C.

4.4.5 Laying

 

a.    The bitumen macadam shall be laid by machine. Laying shall not proceed under unsuitable weather conditions. The machine used for laying shall preferably be a self-propelled type and capable of laying bitumen automatically to an even, smooth and compact surface to the required widths, thickness and cross falls without segregation of the bitumen macadam.

 

4.4.6 Compaction

 

a.    As soon as rolling can be affected without causing displacement, the bitumen macadam shall be uniformly compacted by rolling. Compaction shall be carried out with a roller or rollers of weight not less than 6 tons nor exceeding 10 tons and the width of the roll shall not be than 450mm. The bitumen macadam shall be rolled in a longitudinal direction working from the sided to the centre of the carriageway, overlapping on successive passes by at least one half of the width of the rear roll. The roller shall be fitted with a quick reverse and smooth acting clutch. Rollers shall not be allowed to stand on newly laid bitumen macadam when there is a risk that the surface will be deformed thereby.

 

b.    Finished road surfaces are to remain without traffic for two days after laying of the wearing course.

 

4.4.7 Laying Interval

 

a.    The wearing course shall be laid on the bitumen macadam base course as soon as practicable. No part of the base course shall be left uncovered by the wearing course for longer than three (3) days unless extension of this period is approved by COMPANY due to suitable weather for laying. During this intervening period unless the work consists of resurfacing, no traffic, other than used in connection with the provision of the wearing course, shall be permitted on the surface of the base course.

 

4.4.8 Joints

 

a.     All joints shall be cut back to a vertical face and painted with hot binder before the adjoining surfacing is laid.

4.4.9 Tolerance in Surface Level and Minimum Compaction Thickness

 

a.     The bitumen macadam wearing course shall be laid by machine in single course and the average compacted thickness of the course shall be as shown on the drawings. The accuracy of finish on the longitudinal direction shall be determined by measuring the gap under 3m straight edge placed in any position of the road surface parallel to the centre line, the gap at any place between the points at which the road should not exceed +/-6mm. The transverse profile shall also confirm to a similar standard or accuracy using a correct shaped template instead of a straight edge. The compacted thickness of the two macadam courses shall nowhere be less than the specified thickness as shown on the drawings after compaction.

4.5    Bituminous Pavement Mix

 

a.     The mineral constituents shall be combined to the following graduation.

 

b.     For Bitumen macadam base Course with binder content 3.8%-4.8%:

 


Metric Sieve      % passing by weight

 

25mm    - 100

 

20mm   - 90-100

 

12.5mm  - 50-80

 

6.3mm   15-35

 

3.15mm mm   5-20

 

0.075mm mm   2-6



 

c.      For Dense Bitumen Macadam wearing Course with binder content 4%-5%:

 


Metric Sieve        % passinbweight

 

20mm  - 100

 

12.5mm  -  90-100

 

6.3mm - 20-40

 

3.15mm - 10-20

 

0.075mm - 2-6


 

4.5.1 The aggregate shall be surfaced dry, and the aggregate and binder separately heated to within the following ranges before entering the mixer:

 


a. Aggregate

 

b. Binder


660C-1490C (1500F-3000F)

 

940C-1630C (2000F-3250F)


 

 

4.5.2 It is particularly important to avoid overheating of the binder and excessively high temperatures of the aggregate at the time of mixing, as these will adversely affect the quality of the resultant Macadam. Materials including any added filler shall be weighed or measured before being put into a mechanical mixer and thoroughly mixer until all particles of the aggregates are completely and uniformly coated.

4.6    Wet mix Macadam Road

 

Wet mix macadam roads shall consist of a layer of compacted granular sub-base material followed by a layer of compacted wet mix macadam materials. Refer to drawings for material thickness.

4.7    Crushed Gravel Surfacing

 

Crushed gravel surfacing shall consist of clean, hard natural gravel or crushed stone conforming to gradation of 100 mm nominal gravel size, as per specification. Crushed gravel surfacing shall be spread after installation of services and cables and suchlike, it shall be spread where indicated on a properly levelled or graded surface, free from weeds, to a compacted thickness on 100mm and lightly rolled.

 

5.0 CONCRETE ROAD PAVING

 

5.1    Concrete paving shall have 30MPa reinforced concrete.

5.2    In areas where heavy maintenance cranes are anticipated around equipment, the concrete paving shall be specially designed to take such crane loads.

5.3    In areas where heavy maintenance cranes are anticipated around equipment, the concrete paving shall be specially designed to take such crane loads.

 

6.0 FIELD TEST

 

6.1    The number and frequency of the field density tests of the control of the compaction of the placed shall be as follows:

 

a.       A minimum of one test per lift shall be made.

 

b.       Material and compaction testing services shall be arranged and paid by CONTRACTOR.

 

7.0 PERMANENT PAVEMENT MARKINGS

 

7.1    This work shall consist of furnishing all materials equipment labour and applying permanent markings on the compacted road pavement for the delineation of shoulders and parking lots.

7.2    Traffic paint shall conform to AASHTO M248 Type F. Stripes shall be a minimum of 10cm wide, for which the minimum rate of paint application shall be 1 litre per 25m length.

 

8.0 RESURFACING AND REINSTATING EXISTING ROAD

 

8.1    All materials and workmanship required for resurfacing and reinstating roads shall comply with the requirements as specified therein before for the new roads.

8.2    Where existing roads are required to be resurfaced all the weak areas in the existing pavement shall be repair with proper patches using bituminous macadam base course adequately compacted. Where the surface is distorted regularly course of bituminous macadam base course material shall be laid in horizontal layers, each not exceeding 75mm in thickness.

 

8.3 The existing bituminous surfacing shall be scarified to a depth of 15mm and tack coat shall be applied before laying new bituminous surfacing.

Civil engineering

Rahul “Nitin”Gupta (BE Civil Engineering ,PMP,MBA Project Management ) is Project Director of this organization he have 8 years of experience in construction industry .He is experts in Site execution, planning , billing department ,Technical advisor .

0 Comments: