SCOPE 1.1     Purpose

The scope of work for this specification includes preparing sugrade, placing of granular sub-base courses, granular base courses, dense bituminous macadam binders and bituminous concrete for the access and plant roads, as well as the requirements for granular base and concrete roads. In cases where more than one code, regulation, specification and standard apply to the same condition, the most stringent shall be followed. In the event of a conflict between this specification and other specifications or correspondence, the COMPANY shall be consulted and a ruling, in writing, shall be obtained before any work is started.

1.2    Standards

 

1.2.1 All materials, equipment and workmanship shall be governed by, but not limited to, the latest version of the following standards.

1.3    International Standards

 

a. ASTM D698    Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 fft-lbf/ft3 (600 kN-m/m3)

 

b. ASTM D1556 Standard Test Method for Density and the Unit Weight of Soil in place by the Sand Cone Method

 

c. ASTM D1557 Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3))

1.4    Indian Standards

 


a. IS-73

 

b. IS-217

 

c. IS-456

 

d. IS-1201-IS-1220

 

e. IS-3117


Specification for Paving Bitumen

 

Specification for Cutback Bitumen

 

Plain and Reinforced Concrete Code of Practice

 

Method for Testing Tar and Bituminous Materials

 

Bitumen Emulsion for Roads and Allied Applications (Anionic Type)


 

f. IS-8887                    Bitumen Emulsion for Roads (Cationic Type)

 

g. IRC                          Indian Roads Congress Standard Specifications:

 

i.          IRC: 15-2002 Standard Specifications and code of practice for Construction of concrete roads (Third revision).

 

ii.         IRC: 29-1988 Specification for Bituminous concrete (Asphaltic Concrete) for road pavement (First Revision).

 

iii.         IRC: 36-2010 Recommended practice for construction of earth Embankments and Sub-Grade for road works (First Revision).

 

iv.        IRC: 11-1984 Handbook of Quality control for construction of roads and runways (second Revision).


v.                           IRC: 53-2010 Guidelines on use modified bitumen in road construction (Second Revision).

 

1.5    Definitions

 

COMPANY:        The COMPANY means Cairn Energy Pty Limited, and its subsidiaries or authorized representatives.

 

CONTRACTOR: Person(s), company, firm, manufacturers, fabricator or vendor.

 

2.0 EXAMINATION

 

The site shall be examined for work that might affect the construction of the road. Particular attention shall be paid to underground cables, pipes, manholes and roadside drains etc.

 

3.0 MATERIALS

 

3.1    Sub-Base Course Materials

 

3.1.1 The sub-base course materials shall be hard, durable and clean granular materials such as sand, or approved granular material and, shall be free of organic material, clay balls and other deleterious substances.

 

3.1.2 The sub-base material shall be well graded and shall conform to following gradation limits; or approved equal:

 

 

JOB MIX FORMULA

SIEVE ANALYSIS FOR GSB GRADUTION FIXING

SIEVE SIZE (MM)

75

53

26.5

9.5

4.75

2.36

0.425

0.075

40-60MM

100

68.4

41.2

5.2

 

 

 

 

10 MM

100

100

100

82.3

21.6

2.6

0.66

0.5

STONE DUST

100

100

100

100

100

99.64

62.8

12.1

40% OF 40-60 MM

40

27.36

16.48

2.08

0

0

0

0

25% OF 10(12) MM

25

25

25

20.58

5.4

0.65

0.165

0.125

35% OF STONE DUST

35

35

35

35

35

34.874

21.98

4.235

RESULTANT GRADING

100

87.36

76.48

57.66

40.4

35.524

22.145

4.36

REQUIRED RANGE

100

80-100

55-99

35-65

25-55

20-40

10-25

3-10

MID RANGE

100

90

77

40

40

30

17.5

6.5

 

3.2    Wet Mix Macadam Road Base

 

3.2.1 The road base to be placed on top of the granular sub-base shall comprise wet mix macadam material laid to the specified thickness for width, line and levels shown on the drawings. The materials shall be crushed rock, hard durable particles or fragments of rock crushed to the correct sizes, well graded and shall have a grading conform to the following gradation limits or approved equal: