CONSTRUCTION CONTROL
1.1 GENERAL. The heterogeneous nature of soil makes it the most variable construction material with which engineers are required to work. Research in soil mechanics and experience gained recently in constructing large earth embankments have provided additional knowledge toward understanding and predicting the behavior of a soil as a construction material. However, only with careful control can engineers ensure that backfill construction will satisfactorily fulfill the intended functions. Both the contractor and the owner share dual responsibility in achieving a satisfactory product. The contractor is responsible for inspections and tests through his quality control system. The owner’s responsibility is assuring that the contractor’s quality control system is achieving the desired results through its quality acceptance system.
CONTRACTOR QUALITY CONTROL - The contractor is responsible for all of the activities that are necessary to ensure that the finished work complies with the plans and specifications to include quality control requirements, supervision, inspection, and testing. The construction contract special provisions explain the quality control system that the contractor must establish; the technical provisions specify the construction requirements with the tests, inspections, and submittals that the contractor must follow to produce acceptable work.
(1) Prior to construction, the contractor must submit for approval by the Contracting Officer his plan for controlling construction quality. The plan must contain all of the elements outlined in the special provisions and demonstrate a capability for controlling all of the construction operations specified in the technical provisions. The plan must include the personnel (whether contractor’s personnel or outside private firm) and procedures the contractor intends to use for controlling quality, instructions and authority he is giving his personnel, and the report form he will use. The plan should be coordinated with his project construction schedule.
(2) During construction, the contractor is responsible for exercising day by day construction quality control in consonance with his accepted control plan. He must maintain current records of his quality control operations. Reports of his operations must be submitted at specified intervals and be in sufficient detail to identify each specific test.
(3) The prime contractor is responsible for the quality control of all work including any work by subcontractors.
COORDINATION BETWEEN OWNER AND CONTRACTOR - The contractor’s quality control does not relieve the owner from his responsibility for safeguarding the Owner’s interest. The quality assurance inspections and tests made by the Owner may be carried out at the same time and adjacent to the contractor’s quality control operations. Quality control and quality assurance supplement one another and assist in avoidance of construction deficiencies or in early detection of such deficiencies when they can be easily corrected without requiring later costly tear out and rebuild. The remainder of this material discusses the owner quality assurance activities.
OWNER ACCEPTANCE CONTROL ORGANIZATION -
4.2.1 GENERAL. Difficulties in construction of a
compacted backfill can be attributed at
least in part to inexperience of the control personnel in this phase of
construction work or lack of emphasis as to the importance of proper procedure
and control. Since it is essential that policies with regard to control be
established prior to the initiation of construction, thorough knowledge of the
capabilities of the control organization and of the intent of the plans and
specifications is required. Control is achieved by a review of construction
plans and specifications, visual inspection of construction operations and
procedures, and physical testing. A well-organized, experienced inspection
force can mean the difference between a good job and a poor one. A good field
inspection organization must be staffed and organized so that inspection
personnel and laboratory technicians are on the job when and where they are
needed. Thus the organization must have knowledge of the construction at all
times. Prior to construction, the training, guidance, and support required to
ensure that the inspection force is fully competent should be determined. If
experience is lacking, training and supervision become more important and necessary.
(2) Inspection personnel should be made aware of the importance of their work by explaining the engineering features of the design on which the construction requirements are based. Every opportunity should be taken to assemble the inspection force for discussion of construction problems and procedures so that all can gain knowledge from the experience of others. Inspection personnel should be kept informed of all decisions and agreements pertinent to their work that are made at higher levels of administration. They should be advised of the limits of their authority and contact with contractor personnel.
(3) Field training of inspection personnel should include observation of their control techniques and additional instruction on elements of fieldwork requiring correction. Inspection personnel should be instructed in the telltale signs that give visual indications whether sufficient compaction is being applied and proper water content is being maintained. They should develop the ability to determine from visual observations (based on correlations with tests on the project) that satisfactory compaction is being obtained so that considerable emphasis can be placed on such methods as a control procedure rather than relying on field tests alone. Inspection personnel should be capable of selecting locations at which field density and moisture determinations should be made. To meet this requirement they must be present almost continuously during compaction operations to observe and note areas where tests appear to be needed. Laboratory technicians should be made available to perform tests so that the inspection personnel will be free to observe the placement and compaction process on another portion of the backfill. Inspection personnel should be able to use expedient quick-check field apparatus such as the Proctor and hand-cone penetrometers to make a rapid check of the field water content to supplement acceptance testing and to serve as a guide in determining areas that should be tested. Inspection personnel should also be well versed in normal testing procedures so they can properly supervise testing or explain the procedure in case they are questioned by contractor personnel.
FIELD LABORATORY FACILITIES - The field laboratory is used for routine testing of construction materials (such as gradation, water content, compaction, and Atterberg limits tests) and for determining the adequacy of field compaction. The data obtained from tests performed by inspection personnel serve as a basis for determining and ensuring compliance with the specifications, for obtaining the maximum benefit from the materials being used, and for providing a complete record of the materials placed in every part of the project. The size and type of laboratory required are dependent on the magnitude of the job and the type of structures being built. Where excavation and backfill construction are extensive and widespread, the establishment of a centrally located field laboratory is generally beneficial. This laboratory in addition to having equipment for on-the-job control will provide a nucleus of experienced soils engineers or engineering technicians for general supervision and training of inspection personnel. Field control laboratories on the sites may be established as necessary during the excavation and backfill phases of the construction. They may be set up in an enclosed space allocated by the project officer or in mobile testing laboratories, such as pickup trucks with a camper and equipped with the necessary testing equipment for performance of field density tests, water content tests, and gradation tests. Another possibility is the use of large portable boxes in which equipment is stored. When special problems arise and the required testing equipment is not available at the site laboratory, the testing should be performed at the central laboratory.
EXCAVATION CONTROL TECHNIQUES- Control to obtain a satisfactory excavation is exercised by enforcement of approved plans, visual observations, a thorough knowledge of the contractor’s plan of operation and construction schedule, the dimensions and engineering features of the structure(s) to be placed in the excavation, and vertical and horizontal control measurements to ensure that the proper line and grade requirements are met.
FOUNDATION PREPARATION CONTROL
TECHNIQUES. The main control technique for ensuring proper foundation
preparation is visual inspection. Prior to backfill placement, all uncompacted
fill should be removed from those portions of the excavation to be backfilled.
The items included are road fills, loose material that has fallen into
overexcavated areas adjacent to foundations, and construction ramps other than
those required for access to the excavation. Identification of such items will
be easier if the inspection personnel have charted the items on the plans as
they were created, since they are not always easily discernible by visual
inspection. It is desirable to control earth backfill placed in foundation
leveling operations by water content and density tests. Care should be
exercised to ensure that all subdrains required in the foundation are protected
by filters and transitional zones that are adequate to prevent infiltration of
fines from the surrounding backfill that might otherwise clog the drains and
undermine structures.
BACKFILL QUALITY ACCEPTANCE CONTROL- The necessary authority to assure that
compacted backfill is in compliance with the specifications is given in the
specifications. The control consists of inspecting and testing materials to be
used, checking the amount and uniformity of soil water content, maintaining the
proper thickness of the lifts being placed, and determining the dry unit weight
being obtained by the compaction process. While control consists of all of
these things, good inspection involves much more.
including crushing, raking, mixing, and
adjusting of water content, must be done in the stockpile or borrow areas.
(10)
Allowing
material that is too wet or too dry to be compacted.
(11) Failing to require that intermediate backfill surfaces be shaped to drain during backfilling at other locations.
all times and be at the site where backfill
is being placed. The inspection personnel must be thoroughly familiar with
every aspect of the earthwork section of the specifications and know boundary
locations for the various zones of material. They should be able to readily
identify the various classes of backfill and know their compaction
characteristics and requirements. Good inspection personnel will also know the
compaction capabilities of various types of equipment and the materials that
each type is best suited to compact.
(1) To maintain adequate control of compaction operations, a staff of earthwork inspectors and laboratory personnel commensurate with the importance of the work and size of the operation is essential. There should be at least one inspector at the fill when backfill is being placed. His sole duty should be inspection of earthwork. Although he should be familiar with the testing procedures and capable of directing testing operations and selecting locations for testing, he should not be required to perform the tests. Laboratory technicians should be available for this purpose.
(2) The specifications should require that necessary processing of backfill materials be performed in the stockpile or borrow pit. Processing includes raking or crushing to remove oversize material, mixing to provide uniformity, and watering or aerating to attain a water content approximating optimum for compaction. An earthwork inspector is required at the stockpile or borrow pit to enforce these provisions. In addition, this inspector has the duties of classifying the materials, determining their suitability, and directing the zone of backfill in which they are to be placed. He is charged with the responsibility of seeing that the contractor uses the materials available for backfill in the most advantageous manner. Generally, the stockpile or borrow pit inspector relies upon visual inspection and experience to exercise control over these operations. Occasionally, he may require that appropriate tests be performed to confirm his judgment.
(3) The duties of the backfill inspector
consist of checking the material for suitability as it is placed on the fill
and spread, ensuring that any oversize material, roots, or trash found in the
material is removed, checking the thickness of the lift prior to compaction,
checking for uniformity and amount of water content, observing compaction
operations, and directing or monitoring testing of the compacted material for
compliance with density and water content requirements.
(4) There are many techniques and rule-of-thumb procedures that the earthwork inspector can and must resort to for assistance in his work. A few of them are discussed below; others can be ascertained by inspectors meeting together to discuss problems and corrective action.
(a) The thickness of loose lifts can be checked easily by probing with a calibrated rod just prior to compaction. Compaction of lifts too thick for the equipment will not normally be detected by performing density tests on the lift, since adequate compaction may be indicated by a test made in the upper portion of the lift and the lower portion may still have too low a density. It is therefore a requisite that lift thickness be controlled on a loose and thickness basis prior to compaction
(b) Checks for proper bond between layers can be made by digging through a lift after compaction and using a shovel to check this bond. If the soil can be separated easily along the plane between lifts, sufficient bond is not being provided. Backfill materials should not be placed on dried or smooth surfaces, as bond will be difficult to obtain.
4.5.3 COMPACTION CONTROL TESTS. Compaction tests will have been
performed on representative specimens obtained from exploratory sampling prior
to construction. The selection of suitable backfill material are in fact
generally made based on these and other tests. At least during the early phases
of the backfill operation, density requirements are based on these and in some
cases additional preconstruction compaction tests. Conditions may develop that
require compaction tests during backfill operations to establish new density
requirements. Generally, these changes are the results of backfill material
deviations. The need for additional control tests may be ascertained from
visual observation and changes in compaction characteristics during field
compaction. For most backfill materials, quality acceptance compaction control
tests must be performed according to the procedure in ASTM D 1557, or the
two-point test procedure (App B) for some cohesionless soils where higher
maximum dry densities can be obtained using the vibratory (relative density) compaction.
(1) Rule-of-thumb methods. Rule-of-thumb techniques are derived
from experience and are based on visual observations and feel of the material.
A rule-of-thumb for judging if the water content of a fine-grained, plastic
material is near the optimum water content consists of rolling the material between the hands until it forms a thread approximately.
1/8
inch in diameter. If the material at this stage tends to crack or crumble, it
is in the proper water content range for compaction. It will be recognized that
this method is similar to the method of determining the plastic limit of a
soil. The methods are similar because the optimum water content for compaction
of a cohesive soil roughly approximates the plastic limit of the soil.
(b)
Penetrometers, such as the Proctor and hand cone
penetrometers, are useful under certain conditions for approximating density.
However, both methods
require careful
calibration using soils of known density and water content and considerable operating experience. Even then, the results may be questionable because nonuniform water content (in fine-grained material) or a small piece of gravel can affect the penetration resistance. Penetrometers, therefore, are not recommended for general use in compaction control; however, they can be a very useful tool in supplementing the inspector’s visual observations and providing a general guide for detecting areas of doubtful compaction. The procedure using the Proctor pentameter for determining the relation between wet density, penetration resistance, and water content is described in ASTM D 1558.
(c)
Many inspectors in the past have had good success in
estimating density by simply observing the resistance of the compacted soil to
penetration by a spade. This method requires considerable experience and is
useful only in detecting areas that might require further density tests.
(b) the rubber-balloon method according to ASTM D 2167; and for soft, fine-grained cohesive soils, the drive-cylinder method according to ASTM D 2937. In addition to the approved methods, a method sometimes employed to measure densities of coarse- grained cohesionless material consists of the large-scale, water-displacement method. The sand cone method is considered to be the most reliable method and is recommended as the proof or calibration test for calibrating other methods such as the nuclear density method.
WATER CONTENT BY MICROWAVE OVEN- The biggest problem associated with
both field compaction tests and in-place density and water content control
tests is the length of time required to determine water content. Conventional
ovendrying methods require from 15 to 16 hours for most fine-grained cohesive
soils. In some cases, such as confined zones, the contractor may have placed
and compacted several layers of backfill over the layer for which density tests
were made before quality acceptance test data are available. Even though the
contractor places successive layers at his own risk, a rapid turn around
between testing and test results could prevent costly-tear out and recompact
procedures. Drying specimens in microwave ovens offers a practical means for
rapid determination of water content for most backfill materials if properly
conducted. Times required for drying in a microwave oven are primarily governed
by the mass of water present in the specimen and the power-load output of the
oven. Therefore, drying time must be calibrated with respect to water content
and oven output. Also, it may not be possible to successfully dry certain soils
containing gypsum or highly metallic soils such as iron ore, aluminum rich
soils, and bauxite.
4.7 ERRORS IN FIELD DENSITY MEASUREMENTS. Density and water content measurements determined by any
of the methods discussed above are subject to three possible sources of errors.
The three categories of possible error sources are human errors, errors
associated with equipment and method, and errors attributed to material
property behavior.
(1) Human error includes such factors as
improper equipment readings and following improper test procedures. Human
errors are not quantitative. However, errors of this type may be minimized by
utilizing competent testing personnel familiar with testing procedures.
(3) The primary advantage of statistical
methods is that they offer a means of systematically evaluating acceptance or
rejection decisions rather than leaving such decisions entirely to the judgment
of the inspection personnel. However, if experienced and well trained
inspection personnel are available, this approach may not be necessary.
Planning & billing engineering Book
0 Comments: