CLIENT |
|
|
PROJECT MANAGER |
|
|
CONTRACTOR |
|
|
PROJECT NAME |
- |
|
Sr.No |
Description |
Page No |
1 |
INTRODUCTION |
3 |
2 |
PURPOSE |
3 |
3 |
SCOPE |
3 |
4 |
RESPONSIBILITY |
3 |
5 |
DEFINITIONS / ABBREVIATION |
4 |
6 |
MAJOR RESOURCES DEPLOYED |
4 |
7 |
EQUIPMENT & MATERIAL |
4 |
8 |
PROCEDURE |
5 |
9 |
PERMIT TO WORK |
6 |
10 |
PREPARATION |
6 |
11 |
HEALTH, SAFETY AND ENVIRONMENT |
6 |
12 |
ATTACHMENTS |
7 |
The objective of this method statement is to clearly understand
the job for the execution of the job along with safety precautions, which are
necessary to avoid any kind of injuries / accidents to personnel or any damage
to any equipment or property. We have prepared this method statement for the situation
clearly stated that how Infinity Interiors will perform the safety Net
Installation works in the tower area.
2.
PURPOSE
The purpose of the water proofing and
all other related works shall be executed as the part of Godrej nature plus Project.
This method statement describes the construction procedure to be followed at
the site.
All activities within the project scope of work are carried out safely by ------ in strict compliance with HBOCW act.
3.
SCOPE
The scope of this method statement includes but not limited to the
following activities;
·
Material
Handling
·
Level
Checking & Cleaning
·
Floor
Hacking
·
Concreting
4.
RESPONSIBILITY:
a.
Performing
authority/Permit Holder shall be full working time available at site and responsible
for managing all job, machinery and labor for related job.
b. The QA/QC engineer/Inspector shall be
responsible for ensuring the quality of work as per the specifications.
c. Engineer/Supervisor shall be full
working time available at site and responsible to execute and supervise all the
works according to this Method Statement.
d. The safety Supervisor shall be full
working time available at site and responsible to ensure work being executed in
safe manner.
e. Project Manager shall be responsible for
whole work at site.
5.
DEFINITIONS /
ABBREVIATION
COMPANY :
CONTRACTOR :
HSE : HEALTH, SAFETY AND
ENVIRONMENT
PTW :
PERMIT TO WORK.
TBT :
TOOL BOX TALK
QA/QC
: QUALITY ASSURANCE AND QUALITY CONTROL
RA :
RISK ASSESSMENT
§ PVC Strip
§ Leveling
§ Sand
§ Aggregate
§ Cement
§ Water
7.1 Equipment & Materials
The equipment & materials involved
in above mentioned works are mentioned below:
Ø Level Machine
Ø Batch Mixture
Ø Cube Mold
7.2 Man power
The personnel involved in these operations
mentioned as below:
Ø
Safety Supervisor.
Ø
Site Engineer/
Ø
QA/QC Engineer
Ø
Foreman / Charge hand
Ø
Mason
Ø
Helpers
8
PROCEDURE
8.1 Surface preparation: Cleaning
all the dirt and loose matter chipping and cleaning of mortar dropping.
Do prepare the surface on the concrete floor by hacking at close intervals (50
to 70 mm center to center) with bush hammer or with a chisel and hammer and
then wash it thoroughly with water. This will roughen up the concrete surfaces
and ensure a good bond is provided for the IPS concrete.
The surface thus prepared should be uniform, clean and saturated with water for
minimum of 4 hours before concreting.
8.2 Laying Procedure: Fix
the panels dividers (as mentioned in the drawing) in position for diagonally
alternative panels. The panel’s size should not be more that 2.2 M X 1.8 M
(3.96 Sqm).
Ø Dividing
strips of PVC shall be fixed as per the panel layout to correct line and level.
Top of the strip must match with the required slope and finished floor level.
Strip fixing can be done with mortar at least one day in advance.
Ø Do
the concreting in the sequence of laying in alternative panels.
Ø Before
starting IPS concrete laid/spread the cement slurry (1 cement : 4 water) on the
surface.
Ø Base
coarse concrete of given thickness shall be finished rough in first stage. Top
10 to 12 mm thick second layer concrete needs a richer mix with zero fines.
(i.e rich mix as specified with only 6 mm aggregate, cement and hardener if
recommended. No sand to be used.)
Ø Pour
the concrete in the panels, Level and compact the concrete with Double beam
vibrator, to give dense and flat surface.
Ø Start
power floater for grinding the surface (along with leveling it also increases
the water resistance of concrete flooring).
Ø After
completion of concrete check level maintain proper level on the surface.
Ø Use
the power trowels to give desired smooth finish.
Ø Finish
the top surface with Broom, to get required broom finish.
Ø For all trowel finished surfaces, the finishing has to be
completed before the mortar or concrete is fully set.
Carrying out curing for specified period of 7
days.
If needed Groove cutting to be done at required places.
9.1PERMIT TO WORK
Work
permits shall be obtained from GPL (if necessary) it will be followed for all activities.
All safety precautionary measures outlined in respective work permits will be
fully adhered.
9.2 INDUCTION
Ø All
employees including subcontractor’s personnel, on the project site will be
inducted in Safety related matters by Infinity prior to enter to the work site.
Ø The
workforce will be communicated /briefed for HAZARD’s & Minor to minor
injury associated during work within Tower area.
Ø Performing
authority will conduct TBT and brief the hazards and control measures involved
in work before commencement.
10 PREPARATIONS
Ø Material Shifting -:
During the Material
shifting to be followed the Instructions –
1-All workers use necessary PPE’s as per required.
2- Material Handling & Shifting Training.
3- Access area to be cleared.
Material Mixing by Mixture Machine
During the Operating –
1-
Mixture machine should be operated
by trained person.
2-
Mixture machine with inspection
tag.
3-
Mixture Machine operator should be
used goggles, rubber hand gloves & Gun boot also with working same PPE’s
used by all workers.
11
HEALTH,
SAFETY & ENVIRONMENT
Ø All workforces shall attend induction training provided by Infinity
safety person.
Ø All personnel involving in various stages of construction will
attend the “TBT “(Tool box TALK)” conducted prior to start day's activity on
daily basis and will be ensured to make them aware about potential hazards
involved within the work area & relevant safety measures to be taken.
Ø Competent work force will be deployed for the job. They will be
trained for safety requirements and procedures of the job and risks involved in
the job.
Ø Working area should be neat & clean .
Ø First aid facility will be available during working area.
Ø All personnel will have necessary
PPEs.
Ø Adequate drinking water facility and amenities will be provided.
Ø Adequate safety sign boards will
be placed all around the work area.
Ø List of emergency contact
telephone numbers will be made available to all Key personnel associated with
this work for all the time.
Ø All personnel involved in works
shall be aware of Safety requirements of the project and the site shall be kept
clean and tidy conditions all the time.
Ø All access / exit points to work
areas shall be maintained free from obstacles, materials and equipment.
Ø Safety supervision will be made available
continuously and will monitor the activities.
Ø Portable fire extinguishers (ABC 6
Kg) shall be provided at the site wherever necessary.
Ø Risk Assessment (RA) will be
performed to assess the hazards involved and control measures to be taken prior
to start of activity and submitted for Company review. All control measures
will be ensured according to RA.
Ø All the equipment/machineries for
the works will be kept at safe locations.
Ø All worker Mandatory to
nose mask and social distancing due to Covid -19 .
12
ATTACHMENTS
Ø HIRA
(RNIPL-HSE-RA-00)
0 Comments: