    CLIENT


   PROJECT MANAGER


   CONTRACTOR

 

 


 

   PROJECT NAME         

-


 

 TABLE OF CONTENTS - 

 

Sr.No

Description

Page No

1

INTRODUCTION

3

2

PURPOSE

3

3

SCOPE

3

4

RESPONSIBILITY

3

5

DEFINITIONS / ABBREVIATION

4

6

MAJOR RESOURCES DEPLOYED

4

7

EQUIPMENT & MATERIAL

4

8

PROCEDURE

5

9

PERMIT TO WORK

6

10

PREPARATION

6

11

HEALTH, SAFETY AND ENVIRONMENT

6

12

ATTACHMENTS

7

 

 

 

 IPS Work, Concreting associated works.

The objective of this method statement is to clearly understand the job for the execution of the job along with safety precautions, which are necessary to avoid any kind of injuries / accidents to personnel or any damage to any equipment or property. We have prepared this method statement for the situation clearly stated that how Infinity Interiors will perform the safety Net Installation works in the tower area.

2.         PURPOSE

The purpose of the water proofing and all other related works shall be executed as the part of Godrej nature plus Project. This method statement describes the construction procedure to be followed at the site.

 

All activities within the project scope of work are carried out safely by ------ in strict compliance with HBOCW act.

 

3.         SCOPE

The scope of this method statement includes but not limited to the following activities;

·           Material Handling 

·           Level Checking & Cleaning

·           Floor Hacking

·           Concreting

4.         RESPONSIBILITY:

a.       Performing authority/Permit Holder shall be full working time available at site and responsible for managing all job, machinery and labor for related job.

b.       The QA/QC engineer/Inspector shall be responsible for ensuring the quality of work as per the specifications.

c.       Engineer/Supervisor shall be full working time available at site and responsible to execute and supervise all the works according to this Method Statement.

d.       The safety Supervisor shall be full working time available at site and responsible to ensure work being executed in safe manner.

e.       Project Manager shall be responsible for whole work at site.

 

 

 

 

 

5.         DEFINITIONS / ABBREVIATION

 

COMPANY          :   

 

CONTRACTOR    :   

 

HSE                      :  HEALTH, SAFETY AND ENVIRONMENT

 

PTW                    : PERMIT TO WORK.

 

 TBT                     :   TOOL BOX TALK

 

QA/QC              : QUALITY ASSURANCE AND QUALITY CONTROL

 

RA                    : RISK ASSESSMENT

 

 6.         MAJOR RESOURCES DEPLOYED:

§  PVC Strip

§  Leveling

§  Sand

§  Aggregate

§  Cement

§  Water

7.1 Equipment & Materials

 

The equipment & materials involved in above mentioned works are mentioned below:

 

Ø  Level Machine

Ø  Batch Mixture

Ø  Cube Mold

 

7.2 Man power

The personnel involved in these operations mentioned as below:

Ø  Safety Supervisor.

Ø  Site Engineer/

Ø  QA/QC Engineer

Ø  Foreman / Charge hand

Ø  Mason

Ø  Helpers

8         PROCEDURE

8.1 Surface preparation: Cleaning all the dirt and loose matter chipping and cleaning of mortar dropping.
Do prepare the surface on the concrete floor by hacking at close intervals (50 to 70 mm center to center) with bush hammer or with a chisel and hammer and then wash it thoroughly with water. This will roughen up the concrete surfaces and ensure a good bond is provided for the IPS concrete.
The surface thus prepared should be uniform, clean and saturated with water for minimum of 4 hours before concreting.

8.2 Laying Procedure:  Fix the panels dividers (as mentioned in the drawing) in position for diagonally alternative panels. The panel’s size should not be more that 2.2 M X 1.8 M (3.96 Sqm).

Ø  Dividing strips of PVC shall be fixed as per the panel layout to correct line and level. Top of the strip must match with the required slope and finished floor level. Strip fixing can be done with mortar at least one day in advance.

Ø  Do the concreting in the sequence of laying in alternative panels.

Ø  Before starting IPS concrete laid/spread the cement slurry (1 cement : 4 water) on the surface.

Ø  Base coarse concrete of given thickness shall be finished rough in first stage. Top 10 to 12 mm thick second layer concrete needs a richer mix with zero fines. (i.e rich mix as specified with only 6 mm aggregate, cement and hardener if recommended. No sand to be used.)

Ø  Pour the concrete in the panels, Level and compact the concrete with Double beam vibrator, to give dense and flat surface.

Ø  Start power floater for grinding the surface (along with leveling it also increases the water resistance of concrete flooring).

Ø  After completion of concrete check level maintain proper level on the surface.

Ø  Use the power trowels to give desired smooth finish.

Ø  Finish the top surface with Broom, to get required broom finish.

Ø  For all trowel finished surfaces, the finishing has to be completed before the mortar or concrete is fully set.

Carrying out curing for specified period of 7 days.
If needed Groove cutting to be done at required places.

 

9.1PERMIT TO WORK

Work permits shall be obtained from GPL (if necessary) it will be followed for all activities. All safety precautionary measures outlined in respective work permits will be fully adhered.

9.2 INDUCTION

Ø All employees including subcontractor’s personnel, on the project site will be inducted in Safety related matters by Infinity prior to enter to the work site.

Ø  The workforce will be communicated /briefed for HAZARD’s & Minor to minor injury associated during work within Tower area.

Ø  Performing authority will conduct TBT and brief the hazards and control measures involved in work before commencement.

 

10 PREPARATIONS

Ø  Material Shifting -:

                                      During the Material shifting to be followed the Instructions –

1-All workers use necessary PPE’s as per required.

2- Material Handling & Shifting Training.

3- Access area to be cleared.

 

Material Mixing by Mixture Machine

 During the Operating –

1-      Mixture machine should be operated by trained person.

2-      Mixture machine with inspection tag.

3-      Mixture Machine operator should be used goggles, rubber hand gloves & Gun boot also with working same PPE’s used by all workers.

11     HEALTH, SAFETY & ENVIRONMENT

 

Ø  All workforces shall attend induction training provided by Infinity safety person.

Ø  All personnel involving in various stages of construction will attend the “TBT “(Tool box TALK)” conducted prior to start day's activity on daily basis and will be ensured to make them aware about potential hazards involved within the work area & relevant safety measures to be taken.

Ø  Competent work force will be deployed for the job. They will be trained for safety requirements and procedures of the job and risks involved in the job.

Ø  Working area should be neat & clean .

Ø  First aid facility will be available during working area.

Ø  All personnel will have necessary PPEs.

Ø  Adequate drinking water facility and amenities will be provided.

Ø  Adequate safety sign boards will be placed all around the work area.

Ø  List of emergency contact telephone numbers will be made available to all Key personnel associated with this work for all the time.

Ø  All personnel involved in works shall be aware of Safety requirements of the project and the site shall be kept clean and tidy conditions all the time.

Ø  All access / exit points to work areas shall be maintained free from obstacles, materials and equipment.

Ø   Safety supervision will be made available continuously and will monitor the activities.

Ø  Portable fire extinguishers (ABC 6 Kg) shall be provided at the site wherever necessary.

Ø  Risk Assessment (RA) will be performed to assess the hazards involved and control measures to be taken prior to start of activity and submitted for Company review. All control measures will be ensured according to RA.

Ø  All the equipment/machineries for the works will be kept at safe locations.

Ø  All worker Mandatory to nose mask and social distancing due to Covid -19 .

 

12     ATTACHMENTS

Ø  HIRA (RNIPL-HSE-RA-00)

 