Headlines
Loading...

Construction QC/QA Plan

                                SECTION 1

 NTRODUCTION - 

The United States Environmental Protection Agency (EPA) issued a Superfund Record of Decision (ROD) on February 1, 2002 (EPA, 2002) calling for, among other things, the dredging and disposal of certain sediments from the Upper Hudson River containing polychlorinated biphenyls (PCBs). On August 18, 2003, the General Electric Company (GE) and EPA entered into an Administrative Order on Consent for Hudson River Remedial Design and Cost Recovery (RD AOC) (Index No. CERCLA-02-2003- 2027) (EPA/GE, 2003), under which GE agreed to design the remedy outlined in the ROD.

 

On October 6, 2005, the Consent Decree (CD) for the remedial action (RA) in the Upper Hudson River (Civil Action 1:05-CV-1270) was filed in Federal Court. After an extensive public review and comment period, the court approved and entered the CD as a final judgment on November 2, 2006, when it went into effect (EPA/GE, 2005).

 

GE prepared the Phase 1 Final Design Report (FDR) (BBL, 2006) and submitted it to EPA on March 21, 2006. On May 31, 2006, EPA approved the portion of the FDR that included the facility site work construction (Contract 1) and rail yard construction (Contract 2). However, EPA has not yet approved the designs for the access road and the work support marina.

 

Included as Appendix B to the CD is the Statement of Work for Remedial Action and Operations, Maintenance and Monitoring (SOW) which sets forth a number of requirements for implementing the remedial action set forth in the ROD. Section 2.1.2 of the SOW requires that a Construction Quality Control / Quality Assurance Plan (CQAP) be provided to EPA for review and approval. This document is being submitted to satisfy that requirement.

 

1.1 PROJECT SETTING

 

The Upper Hudson River is defined as the section of river from the Fenimore Bridge in Hudson Falls to the Federal Dam at Troy, New York. The ROD calls for, among other things, a remedial action to remove and dispose of sediments from the Upper Hudson River. Sediments to be removed are defined based on the PCB mass per unit area (MPA) and surface concentration or characteristic criteria (EPA, 2002).

 

EPA defined three sections of the Upper Hudson River for the sediment remediation activities outlined in the 2002 ROD:

 

    River Section 1: Former location of Fort Edward Dam to Thompson Island Dam (TID) (from river mile [RM] 194.8 to RM 188.5; approximately 6.3 river miles);

 

Construction QC/QA Plan

 

    River Section 2:     TID to Northumberland Dam (from RM 188.5 to RM 183.4; approximately 5.1 river miles); and

    River Section 3: Northumberland Dam to the Federal Dam at Troy (from RM 183.4 to RM 153.9; approximately 29.5 river miles).

 

The remedial action is to be conducted in two phases, designated Phase 1 and Phase 2. Phase 1 is defined as the first year of dredging and will be completed in a portion of River Section 1. Phase 1 also includes preparation of the land-based sediment processing facility. Phase 2 covers the remaining dredging in the three river sections.

 

1.2 PHASE 1 CONTRACTS DESCRIPTION

 

The project scope for Phase 1 activities will be conducted under at least seven separate contracts (excluding the rail transport and disposal contracts as well as agreements with the originating rail carrier for infrastructure improvements) and three separate Remedial Action Work Plans (RAWPs). The contracts and RAWPs are described below and summarized in Table 1-1. The table also includes the relationship of construction quality assurance (QA), quality control (QC) and health and safety to other Phase 1 activities.

 

Table 1-1. Organization of Phase 1 RA Work Plans

 

 

Phase 1 Contract Packages

 

Remedial Action Work Plans

 

Construction Quality Assurance Plans

 

Remedial Action Health and Safety Plan

Contract 1 – Facility Site Work Construction

RA Work Plan #1

 

Phase 1 Facility Site Work Construction

Construction Quality Control/Quality Assurance Plan

One umbrella

RA Health and Safety Plan

Contract 2 – Rail Yard Construction

 

Contract 3A – Processing Facility Construction

RA Work Plan #2

 

Phase 1 Processing Equipment Installation and Remaining Site Work

Contract 3B – Processing Facility Operation

RA Work Plan #3

 

Phase 1 Dredging and Facility Operations

Dredging Construction Quality Control/Quality Assurance Plan

Contract 4 – Dredging Operations

Contract 5 – Habitat Construction

Contract 6 – Rail Yard Operations

 

The activities to be performed under Contract 1 (Facility Site Work Construction) and Contract 2 (Rail Yard Construction) are presented in detail in Sections 2 through 7 of RAWP #1,

Construction QC/QA Plan

 

Remedial Action Work Plan for Phase 1 Facility Site Work Construction (Parsons, 2007). These activities include the following:

 

    Contract 1 Facility Site Work Construction includes general civil work, such as grading, placement and compaction of fill and paving. Other work activities include wharf area construction, access road construction, river mooring installation and construction of a support marina.

    Contract 2 Rail Yard Construction includes rail construction on the processing facility site property, and within the right-of-way of the commercial rail carrier, and rail yard facilities work.

 

The activities to be performed under Contract 3A Processing Equipment Installation will be described in RAWP #2, Remedial Action Work Plan for Phase 1 Processing Equipment Installation and Remaining Site Work. RAWP #2 covers the remaining site work, such as processing facility buildings, and the installation of process equipment, piping, electrical, instrumentation, communications, and the commissioning of the systems.

 

The scope of work under Contract 3B, Contract 4, Contract 5, and Contract 6 will be addressed in RAWP #3, Remedial Action Work Plan Phase 1 Dredging and Processing Facility Operations. Briefly, RAWP #3 covers the following:

 

    Contract 3B Processing Facility Operations, including barge offloading, coarse material separation, sediment dewatering, water treatment (process and stormwater), stormwater management, and staging area management and maintenance. In the off season (when the Champlain Canal is closed), the contractor will winterize the processing facility and operate and maintain the stormwater collection and treatment system.

    Contract 4 Dredging Operations, including resuspension containment system installation, debris removal, the performance of inventory and residual dredging operations and the transport of loaded sediment barges to the off-loading wharf at the processing facility. After dredging is completed in an area, the contractor will place appropriate backfill, cap, or shoreline stabilization structures.

    Contract 5 Habitat Construction, including the supply and planting of subaquatic vegetation in certain dredged areas pursuant to habitat reconstruction plans.

    Contract 6 Rail Yard Operations, including all activities required to operate and maintain the rail yard.                    This primarily will involve the loading of debris, coarse material and dewatered sediment into empty rail cars, setting up of outbound loaded trains, and receiving of inbound empty trains.

 

1.3 QUALITY PROGRAM OVERVIEW

 

GE's approach to management of the quality of the RA implementation includes a combination of quality control by the contractor and quality assurance by the Construction

1-3


Construction QC/QA Plan

 

Manager. The CQAP details the systems and controls that GE has put in place so that the quality of the project will meet the requirements specified in the Phase 1 FDR. GE provides definition and overall management of the quality approach to be followed by its contractors and consultants. The quality of the RA implementation will be ensured through an integrated system of quality assurance performed by the Construction Manager and quality control provided by the contractors. GE's Construction Manager is responsible for the day-to-day coordination of quality assurance and quality control measures in the field.

 

This Construction Quality Control/Quality Assurance Plan (CQAP) is a companion document to RAWP #1 and RAWP #2. It establishes:

 

    project procedures and general responsibilities for the quality assurance and quality control (QC/QA) program; and

 

    protocols to ensure that the Phase 1 Facility Site Work Construction (FSWC) and Process Equipment Installation (PEI) will be executed in accordance with the relevant portions of the Phase 1 FDR.

 

This CQAP has been developed in accordance with Section 2.1.2 of the SOW.

 

The contractors are responsible for constructing the work in accordance with the plans and specifications. Each contractor is also responsible for controlling the quality of its work to meet contract plans, specifications, and related requirements. The contractor’s QC is the systematic implementation of a program of inspections, tests, and production controls to attain the required standards of quality and to preclude problems resulting from noncompliance.                                        Pursuant to Technical Specification Section 01400 Quality Requirements, each contractor will establish an independent QC program and write a Contractor Quality Control Plan (CQCP). The CQCP must provide for tests and inspections pursuant to various technical specifications. It will define procedures to ensure that activities affecting quality are properly documented and accomplished in accordance with contract documents; written instructions; and industry standards, codes and procedures. Furthermore, the CQCP will define methods for ensuring that activities affecting quality will be accomplished under controlled conditions.

 

Independently of the contractors, the construction manager (CM) will provide QA through daily monitoring and scheduled inspections to verify the effectiveness of the contractor’s QC program and assure that the quality and contract requirements are met by the contractors. The CM assures that the contractor’s QC is working effectively, and that the resultant construction complies with the quality requirements established by the contract.

 

The objectives of this CQAP are to:

 

    Describe the quality program and organization to be implemented so that the project is constructed in accordance with the contract requirements and industry standards.

 


Construction QC/QA Plan

 

     Describe guidelines for inspection and documentation of construction activities;

 

    Provide reasonable assurance that the completed work will meet or exceed the requirements of the construction drawings and specifications; and

    Describe how any unexpected changes or conditions that could affect the construction quality will be detected, documented, and addressed during construction.

 

1.4 QUALITY MANAGEMENT PLAN

 

Parsons Engineering of New York, Inc. (Parsons) has been retained to provide construction management services for this project. As GE’s managing contractor, Parsons will carry out work on this project in accordance with the Parsons Quality Management Plan (QMP) (Parsons, 2005), which was submitted to EPA on November 1, 2005.

 

1.5 CQAP ORGANIZATION

 

This CQAP is organized into eleven sections.

 

    Section 1 - Introduction: describes the project setting, the Phase 1 contracts and related RAWPs, and the CQAP quality program overview.

    Section 2 - Project QC/QA Organization: presents the organizations and key personnel involved in the construction of the RA, their responsibilities and authorities, the structure of the QC/QA organization and the minimum training and experience of the Construction Quality Assurance Officer (CQAO) and personnel.

    Section 3 - Submittals: presents the procedures for processing submittals from Phase 1 contractors and vendors.

    Section 4 - Performance Monitoring Requirements: addresses QC/QA for performance monitoring requirements applicable to Phase 1 FSWC and PEI.

    Section 5 - Inspection and Verification Activities: provides procedures for tracking construction inspection and verification activities for the contract, construction acceptance criteria, and construction audits.

    Section 6 - Construction Deficiencies: describes the procedures for tracking construction deficiencies from identification through acceptable corrective action.

    Section 7 - Documentation: describes the procedures for the project documents that will be managed through a combination of a secure document filing and storage system and computerized Document Tracking System.

    Section 8 - EPA Approvals: describes EPA approvals applicable to the Phase 1 FSWC and PEI QC/QA.

    Section 9 - Field Changes: describes handling of quality plan changes to assure QC/QA objectives are met.

Construction QC/QA Plan

    Section 10 - Final Reporting: describes the QC/QA documentation for Phase 1 FSWC and PEI to be submitted to EPA in the Phase 1 Construction Completion Report.

    Section 11 - References: provides bibliographic references to key documents referred to in the body of the plan.

Construction QC/QA Plan

SECTION 2

PROJECT QC/QA ORGANIZATION

This section presents the responsibilities and authorities of organizations and key personnel involved in the construction of the RA, the structure of the QC/QA organization, the minimum training and experience of the QC/QA personnel, and the QC/QA training given to all onsite workers.

2.1 RESPONSIBILITIES AND AUTHORITIES OF ORGANIZATIONS

The organizations involved in the Phase 1 FSWC and PEI and their QC/QA roles and responsibilities are as follows.

2.1.1 Environmental Protection Agency

EPA is the lead agency responsible for observing and monitoring the progress of the Phase 1 FSWC and PEI in accordance with the CD. As such, EPA exercises approval authority for this CQAP.

2.1.2 General Electric Company

GE is responsible for implementing the RA in accordance with the CD and for ensuring that its contractors and subcontractors perform RA construction in accordance with the CD.

The CQAP details the systems GE has put in place in order that its responsibilities to quality are met. GE is responsible for verifying that the CM it has retained effectively implements and manages the systems detailed in the CQAP. GE is also responsible for formal communications with and submittals to EPA.

2.1.3 Engineer of Record

 

The Engineer of Record is an independent, duly qualified, licensed design professional, retained directly by GE to provide design and engineering services in connection with the project. This definition includes all subcontractors to the Engineer of Record.

 

Blasland, Bouck and Lee, Inc. (BBL) is the Engineer of Record for Phase 1 except for the rail yard. HDR Engineering, Inc. (HDR) is the Engineer of Record for the rail yard. BBL and HDR provide submittal review and resolution of design issues as they arise during construction.

 

2.1.4 Construction Manager

The CM is a duly qualified entity retained by GE to provide professional construction management and related services in connection with the project. The CM is responsible for

implementation of this CQAP.

 The CM will manage construction contractors on behalf of GE

 Construction QC/QA Plan

and serve as the primary point of contact with the contractors for all communications to and from the contractors.             The CM will provide Quality Assurance and monitor the day-by-day construction quality control activities performed by construction contractors to verify compliance with the contract plans and specifications. The CM will also manage, coordinate, and administer all QC/QA activities and requirements, including those of subcontractors to the CM. Additionally, the CM may be assigned management of any third party QA inspection and testing firms retained by GE.

2.1.5 Construction Contractors

The construction contractors are retained by GE to provide the labor, materials and equipment required to construct the project in accordance with the contract documents. Construction contractors are responsible for the quality control of their constructed work product as well as the necessary inspections and tests required to ensure that their work complies with the contract documents. They exercise authority over their workforce, including QC personnel and their third-party QC support services.

Pursuant to Specifications Section 01450, each contractor will submit a QC organization chart developed to show all QC personnel and how these personnel integrate with other management, production and construction functions and personnel. All QC staff members are subject to acceptance by GE. The requirements for the QC organization include a QC Systems Manager and a sufficient number of additional qualified personnel to ensure contract compliance. The contractor is to provide a QC organization that is represented on the site at all times during progress of the work and with authority to take any action necessary to ensure compliance with the contract.

2.2 STRUCTURE OF QC/QA ORGANIZATION

The QC and QA functions of the project organizations are functionally integrated although contractually separate. Figure 2.1 shows the functional structure of the project QC/QA team.

  RESPONSIBILITIES AND AUTHORITIES OF KEY PERSONNEL

Key personnel involved in the Phase 1 FSWC and PEI and their QC/QA roles and responsibilities are described below in Section 2.3.1 and Section 2.3.2. Pursuant to the CD statement of work, names of QC/QA personnel assigned CQAP functions are to be communicated to EPA; these personnel are the CQAO and CM Field Inspectors.                      Since personnel assignments are subject to change over time, the CM will maintain a CQAP Staffing List of CQAP personnel assignments including each person’s role and organization. This CQAP Staffing List is initially provided in Attachment 1 together with resumes of current CQAP personnel. When personnel changes occur, GE will provide an updated Attachment 1 to EPA.

  Construction QC/QA Plan

 Construction Manager’s Quality Assurance Personnel .

Construction Manager

The Construction Manager (CM) is the primary point of contact for GE on all construction management issues. The CM is responsible for the overall management of activities related to the construction program, including the implementation of the CQAP and the health and safety program. As such, the CM will work directly with GE to exercise approval authority over contractor submittals including the CQCP. The CQCP must include the names and qualifications of contractor’s QC personnel pursuant to Section 2.3.2 below.

Site Manager

The Site Manager (SM) monitors and works with GE to approve each contractor’s quality, and progress submittals to ensure that the project is meeting the contract requirements. The SM will manage the field implementation of the CQAP at the project sites under control of the senior field engineer (FE) and the Construction QA Officer.

Construction Quality Assurance Officer

The CQAO is a full-time employee of the CM. The CQAO should have a minimum of five years of experience in related construction and prior QA experience on a project of comparable size and scope to this project. Additional qualifications for the CQAO include one or more of the following requirements:

    P.E. with one year of related construction experience acceptable to GE.

   Engineer in Training (EIT) with two years of related construction experience acceptable to GE.

   Three years of related experience acceptable to GE with a Bachelor of Science Degree in civil engineering, civil engineering technology, or construction.

   Construction materials technician certified at Level III by National Institute for Certification in Engineering Technologies (NICET).

The CQAO reports directly to the CM. The CQAO will have full authority delegated by the CM and GE to institute actions necessary for the successful implementation of the QC/QA program to ensure compliance with the contract plans and technical specifications (including stop-work authority). The CQAO is assigned to the project full time.

The CQAO works with GE to administer and implement the CQAP.    This includes controlling this CQAP, making revisions as necessary, and implementing systematic actions to ensure compliance with the plan. The CQAO coordinates activities with the SM to ensure that the FE, inspection staff, third party inspection and testing firms as well as contractor QC staff carry out the requirements of the CQAP.

Construction QC/QA Plan

The CQAO is supported by Parsons’ QA Services. Parsons QA staff will provide expertise, on an as-needed or as-requested basis, in the investigation and handling of significant or unique quality issues.

The CQAO tracks and reports non-conformances to the CM, SM, and after notification to the CM, to contractor management and contractor QC staff. The CQAO also has full authority to obtain direct access to contractor QC files. Other CQAO responsibilities include:

Reviewing contractor QC reports, tests, and inspection results;

Facilitating the implementation of the four-phase inspection program and participating in the required inspections; and

Ensuring that QA personnel conducting inspections are adequately trained and understand assignment limits and time frames.

Senior Field Engineer

The Senior Field Engineer (FE) administers the contract requirements, including the CQCP submittals by contractors, and assures that each contractor consistently conforms to its approved CQCP. The FE oversees inspection efforts, provides technical advice, and coordinates support from engineering support, administration, inspection services, safety, and other team members.

The FE coordinates resolution of unsatisfactory work items with contractors through final acceptance.     The FE assures open noncompliance report (NCR) items are completed and accepted in a timely fashion. Acting in concert with GE, the SM and CQAO, the FE has the authority to require changes to the contractor’s QC organization and plan as required to address apparent trends, to mitigate future NCRs and to obtain the quality specified in the contract documents.

The FE reviews QC and QA testing documentation with contractors, engineers, and inspectors. The FE also reviews plans and specifications for assigned projects and estimates the type and number of QA tests that should be accomplished for each specification section. The FE meets with third-party testing and inspection firms to review test requirements and coordinate testing and inspection services.

Field Inspectors

CM Field Inspectors (FIs) are responsible to the FE and support the FEs administration of the construction contracts. The FIs will hold a bachelors degree in engineering or construction and have three years experience in the type of work being performed on this project, or will have at least five years of related experience and will hold the construction materials technician certified at Level III by the NICET. Certification at an equivalent level by a state or nationally recognized organization will be acceptable in lieu of NICET certification. For inspection of the NY Route 196 intersection construction, QA inspectors must meet NICET Level II or higher .

Construction QC/QA Plan

certification in highway construction. Additional experience and training may be substituted for educational requirements, subject to GE’s approval.

The FIs will monitor the day-to-day activities of the contractor. This includes ensuring that contractors comply with the plans and specifications, applicable building codes, good workmanship, and the QC requirements of the contract. As part of this effort, FIs will:

    conduct independent inspections to verify the quality of the work;       participate in contractor four phase inspections;

    review test and inspection reports; and

    ensure that the required documentation is submitted.

The FIs must be alert to detecting, recording, and reporting any deviation from the contract documents, including calling any deficient item to the attention of the FE, the contractor’s superintendent, and/or other representative. The FIs must keep accurate and detailed records of the contractor’s performance and progress, delivery of materials, and other pertinent matters, including the daily inspection report.

 Contractor’s Quality Control Personnel

QC Systems Manager

The QC Systems Manager (QCM) is a full-time employee of the contractor, or a consultant engaged by the contractor. The QCM should have a minimum of five years of experience in related construction and prior QC experience on a project of comparable size and scope to the contractor’s scope of work on this project. Additional qualifications for the QCM include at least one of the following requirements:

PE with one year of related construction experience acceptable to the CM.

EIT with two years of related construction experience acceptable to the CM.

An individual with three years of related experience acceptable to the CM, with a Bachelor of Science Degree in civil engineering, civil engineering technology, or construction.

Construction materials technician certified at Level III by the NICET.

The QCM will have full authority to institute any and all actions necessary for the successful implementation of the QC program to ensure compliance with the contract plans and technical specifications.    The QCM shall report directly to a responsible officer of the construction contractor. The QCM is assigned to this project full time.

QC Technicians

The contractor QC Technicians perform the following functions:

  Construction QC/QA Plan 

    Inspect all materials, construction, plant, and equipment for conformance with the technical specifications; and

     Perform all QC tests as required by the technical specifications.

Contractor QC Technicians will be engineers, engineering technicians, or experienced craftsmen with qualifications in the appropriate field equivalent to NICET Level II or higher construction materials technician, and will have a minimum of two years of experience in their area of expertise. For inspection of the NY Route 196 intersection construction, QC inspectors must meet NICET Level II or higher certification in highway construction. Certification at an equivalent level by a state or nationally recognized organization will be acceptable in lieu of NICET certification. Additional experience and training may be substituted for educational requirements, subject to GE’s approval.


Rahul “Nitin”Gupta (BE Civil Engineering ,PMP,MBA Project Management ) is Project Director of this organization he have 8 years of experience in construction industry .He is experts in Site execution, planning , billing department ,Technical advisor .

1 comment