1.
INTRODUCTION
This Method Statement describes the methodology to execute all activities
for Safety Net Installation and area
preparation within tower area includes – Installation of pipes, Tie off net and
all relevant associated works.
The objective of this method statement is to clearly understand
the job for the execution of the job along with safety precautions, which are
necessary to avoid any kind of injuries / accidents to personnel or any damage
to any equipment or property. We have prepared this method statement for the situation
clearly stated that how KSC will perform the safety Net Installation work in
the tower area.
2.
PURPOSE
The purpose of the water proofing and
all other related works shall be executed as the part of Godrej nature plus Project.
This method statement describes the construction procedure to be followed at
the site.
All activities within the project scope of work are carried out safely by
KSC in strict compliance with HBOCW act.
3.
SCOPE
The scope of this method statement includes but not limited to the
following activities;
·
Installation
of pipes.
·
Clamping
of pipes.
·
Tie
Off net with 12 mm rope.
·
Pushing
out pipe net outside ward.
·
House
Keeping
4.
RESPONSIBILITY:
a.
Performing
authority/Permit Holder shall be full time available at site and responsible
for managing all job, machinery and labor for related job.
b. The QA/QC engineer/Inspector shall be
responsible for ensuring the quality of work as per the specifications.
c. Engineer/Supervisor shall be full time
available at site and responsible to execute and supervise all the works
according to this Method Statement.
d. The safety Supervisor shall be full time
available at site and responsible to ensure work being executed in safe manner.
e. Project Manager shall be responsible for
executing the work in safer manner.
5.
DEFINITIONS /
ABBREVIATION
COMPANY : Client Name
CONTRACTOR
: Company Name
HSE : HEALTH, SAFETY AND ENVIRONMENT
PTW : PERMIT TO WORK.
TBT : TOOL
BOX TALK
QA/QC : QUALITY ASSURANCE AND QUALITY CONTROL
RA : RISK ASSESSMENT
6. MAJOR RESOURCES DEPLOYED:
7.1 Equipment & Materials
The equipment & materials involved in above mentioned works are mentioned below:
Ø Spanner set.
Ø Net
Ø Pipe
Ø Clamps
Ø Rope.
7.2 Man power
The personnel involved in these operations
mentioned as below:
Ø
Safety Supervisor.
Ø
Site Engineer/
Ø
QA/QC Engineer
Ø
Foreman / Charge hand
Ø
Scaffoldder.
Ø
Helpers
7. PROCEDURE
8.1PERMIT TO WORK
Work
permits shall be obtained from GPL (if necessary) it will be followed for all activities.
All safety precautionary measures outlined in respective work permits will be
fully adhered.
8.2 INDUCTION
Ø All
employees including subcontractor’s personnel, on the project site will be
inducted in Safety related matters by KSC prior to enter to the work site.
Ø The
workforce will be communicated /briefed for HAZARDs associated during work with
in Tower area.
Ø Performing
authority will conduct TBT and brief the hazards and control measures involved
in work before commencement.
8.3 PREPARATION AND NET INSTALLATION.
Ø Unfold the net and inspect the net for any damage
Ø Insert the pipe into reinforcement hook at floor.
Ø Install the pipe with clamp.
Ø Tie the safety Net all around with 12 mm rope.
Ø Extend the pipe outwards up to 3 to 4 meter.
Ø Secure the pipe properly.
Ø Secure the Net properly.
Ø Inspect the Net after installation
8. HEALTH, SAFETY & ENVIRONMENT
Ø All workforces shall attend induction training provided by KSC.
Ø All personnel involving in various stages of construction will
attend the “TBT “(Tool box TALK Meeting)” conducted prior to start day's
activity on daily basis and will be ensured to make them aware about potential
hazards involved within the work area & relevant safety measures to be
taken.
Ø Competent work force will be deployed for the job. They will be
trained for safety requirements and procedures of the job and risks involved in
the job.
Ø First aid facility will be available during work.
Ø All personnel will have necessary
PPEs
Ø Adequate drinking water facility and amenities will be provided.
Ø Adequate safety sign boards will
be placed all around the work area.
Ø List of emergency contact
telephone numbers will be made available to all Key personnel associated with
this work for all the time.
Ø All personnel involved in works
shall be aware of Safety requirements of the project and the site shall be kept
clean and tidy conditions all the time.
Ø All access / exit points to work
areas shall be maintained free from obstacles, materials and equipment.
Ø Safety supervision will be made available
continuously and will monitor the activities.
Ø Portable fire extinguishers (DCP 5
Kg) shall be provided at the site wherever necessary.
Ø Risk Assessment (RA) will be
performed to assess the hazards involved and control measures to be taken prior
to start of activity and submitted for Company review. All control measures
will be ensured according to RA.
Ø All the equipment/machineries for
the works will be kept at safe locations.
9.
ATTACHMENTS- HIRA