SPECIFICATION FOR CONCRETE CONSTRUCTION
SPECIFICATION FOR CONCRETE CONSTRUCTION
1.0 SCOPE
This specification covers the requirements for mixing, forming, reinforcing, placing, curing, testing, finishing and repairing of concrete structures and specifies the materials to be used and material
storage and handling requirements.
2.0 CODES, REGULATIONS AND STANDARDS
2.1 General
CONTRACTOR shall meet or exceed the requirements of the latest edition of the following codes, regulations and standards, except as superseded herein. In cases where more than one
code,
regulation or standard apply
to the same condition, the most stringent
shall be followed. In the
event
of a conflict between this
specification and other specifications or correspondence, the COMPANY shall be consulted and a ruling, in writing,
shall be obtained before any work is started.
Some requirements in this specification may be modified by specific requirements in the project or purchase specifications. In case of conflict, the specific
requirements supersede this specification.
Any deviation from this specification must be accepted, in writing, by COMPANY. Such written acceptance must be obtained prior to the commencement of any
work which would constitute such a deviation.
2.2 International Standards
ACI 309, “Guide for Consolidation of Concrete”
ACI 318, “Building
Code Requirements for Structural Concrete”
2.3 Indian Standards
IS: 73
IS: 2062
IS: 269
IS: 280
IS: 383
IS: 432
IS: 455
IS: 456
IS: 516
IS: 650
IS: 702
IS: 816
IS: 1199
IS: 1367
Specification for paving bitumen.
Specification for structural steel.
Specification for Ordinary Portland
cement,
33 grades.
Specification of mild steel
wire for general engineering purposes.
Specification for coarse and fine aggregates from natural sources for concrete.
Specification for mild steel and medium tensile steel (parts I & II) bars and hard drawn
steel wire for concrete reinforcement.
Specification for Portland slag cement.
Code of practice for plain and reinforced concrete.
Method of test for strength of concrete.
Specification for standard sand for testing of cement.
Specification for industrial bitumen.
Code of practice for use of metal are welding for general construction in mild steel.
Method of measurement of building (part-II, and civil engineering works. V, VIII, XVIII).
Technical supply conditions
for threaded
steel fasteners.
IS: 1489
IS: 1566
IS: 1609
IS: 1786
IS: 1791
IS: 1838(Part I)
IS: 2204
IS: 2386
IS: 2438
IS: 2502
IS: 2505
IS: 2506
IS: 2514
IS: 2571
IS: 2645
IS: 2722
IS: 2750
IS: 2751
IS: 3025
IS: 3067
IS: 3150
IS: 3366
IS: 3370
IS: 3384
IS: 3414
IS: 3550
IS: 3558
IS: 3696
Specification for Portland-pozzolana cement. (Part-I – Fly ash based) (Part-II Claimed clay based).
Specification for Hard-drawn steel wire fabric for concrete reinforcement.
Code of practice for laying damp proof treatment using bitumen felts.
Specification for high strength deformed steel bars and wires for concrete reinforcement.
General requirements for batch type concrete mixers.
Specification for performed fillers for expansion joints in (concrete pavements and
structures (none extruding and resilient type).
Code of practice for construction of reinforced concrete shell roof.
Methods of test of aggregates for concrete (Parts I to VIII).
Specification for roller mixer.
Code of practice for bending and fixing of bars for concrete reinforcement.
General requirements for concrete vibrators, immersion type.
General requirements for concrete vibrators, creed board type.
Specification for concrete vibrating tables.
Code of practice for laying in-situ cement-concrete flooring.
Specification for Integral cement water proofing compounds.
Specification for portable swing weight batchers for concrete. (Single and double bucket type).
Specification for steel scaffoldings.
Code of practice for welding of mild steel plain and deformed bars for reinforced concrete structures.
Methods of sampling and test waste water.
Code of practice for general design details and preparatory work for damp proofing & water proofing
of buildings.
Specification for hexagonal wire netting for general
purposes.
Specification for pan vibrators.
Code of practice for concrete structures for the storage of liquids. (Part I to IV).
Specification for bitumen primer for use in water proofing
& damp proofing.
Code of practice for design and installation of joints in buildings.
Methods of test for routine control for water used in industry.
Code of practice for use of immersion vibrators for consolidating concrete.
Safety code
for scaffolds and ladders (Part I & II).
IS: 4014
IS: 4031
IS: 4130
IS: 4326
IS: 4461
IS: 4656
IS: 4925
IS: 4990
IS: 4995
IS: 5121
IS: 5525
IS: 5624
IS: 6461
IS: 6494
IS: 6509
IS: 7193
IS: 7293
IS: 9103
IS: 9417
IS: 9595
IS: 10262
IS: 11384
IS: 12118
IS: 12200
IS: 12269 53
IS: 12600
SP: 23
SP: 24
Code of practice for steel tubular scaffolding (Parts I & II).
Methods for physical tests for hydraulic cement.
Safety code for demolition
of buildings.
Code of practice for earthquake resistant design and construction of buildings.
Code of practice for joints in surface hydro-electric power stations.
Specification for form vibrators for concrete.
Specification for batching and mixing plant.
Specification for plywood for concrete shuttering
work.
Criteria for design of reinforced concrete bins for the storage of granular and (Parts I & II) powdery materials.
Safety code for piling and other deep foundations.
Recommendations for details of reinforcement in reinforced concrete work.
Specification for foundation bolts.
Glossary of terms relating to cement concrete.
Code of practice for water proofing of underground water reservoirs and swimming pools.
Code of practice for installation of joints in concrete pavements.
Specification for glass fiber base coal-tar pitch and bitumen felts.
Safety code for working with construction machinery.
Specification for admixtures for concrete.
Recommendations for welding cold-worked steel bars for reinforced concrete construction.
Recommendations for metal-arc welding of carbon and carbon manganese steels.
Recommended guidelines for concrete mix design.
Code of practice for composite construction in structural steel and concrete.
Specification for two-part poly supplied.
Code of practice for provision of water stops at transverse contraction joints in masonry and concrete
dams.
Grade ordinary Portland
cement.
Portland cement, low heat.
Handbook of concrete mixes
Explanatory handbooks on IS: 456-1978
SP: 34 Handbook on concrete reinforcement and detailing.
2.4 Other
x National Building Code of India.
x International Building Code (IBC 2003)
x Codes, regulations and Statutes of Authorities having jurisdiction in the location of installation.
3.0 GENERAL
3.1 Definitions
COMPANY:
The COMPANY means Cairn Energy India Pty Limited, and its subsidiaries or authorized representative(s).
CONTRACTOR: Person(s), company, firm, manufacturers,
fabricator or vender.
3.2 Workmanship
Work shall be carried out in accordance with code requirements and industry standards for good workmanship.
4.0 MATERIALS
4.1 General
4.1.1 All materials shall
conform
to IS 456 or ACI 318.
4.1.2 No material other
than that
specified
shall be used
unless accepted,
in writing by COMPANY.
4.2 Storage of Materials
All material shall be stored in accordance with IS 4082.
4.3 Cement
4.3.1 Cement shall
be Portland cement and comply
with IS 269,
IS 8112, IS 12269
or ACI 318, and
shall be as shown on the drawings.
4.3.2 Types of Portland cement:
33 Grade Ordinary Portland Cement
43 Grade Ordinary Portland Cement
53 Grade Ordinary Portland Cement
Rapid Hardening Portland Cement
Sulphate Resistant Portland Cement
Low Heat Portland
Cement
Type of cement shall be used
as per Design brief.
4.4 Aggregates
4.4.1 Aggregates for concrete shall be in accordance with
IS 383 or ACI 318.
4.4.2 The maximum
size of the coarse
aggregates shall be 20 mm unless otherwise noted on the
drawings.
4.5 Admixtures
4.5.1 Air entraining admixtures shall be used in all
concrete to be exposed to weathering
and conform to IS 9103 or ACI 212.3R-04.
4.5.2 No other admixtures shall be used
without COMPANY's written
permission.
4.6 Water
Water used for mixing and curing shall be clean and free from injurious amount of oils, alkalis, salts,
chlorides ions, organic
materials or other substances that may be deleterious to concrete or steel and shall
comply with IS 3025.
Potable water is generally considered satisfactory for mixing concrete. The pH value of water shall be more than 6. Mixing or curing of concrete with sea water is not recommended due
to risk of corrosion of the reinforcement. Such corrosion is accelerated in warm and
humid environments.
4.7 Steel Reinforcement
4.7.1 Reinforcing
shall be new
deformed steel bars or welded wire fabric, as specified on the
drawings.
Steel
bars shall conform to IS 432 (Part 1), IS 1786
and Hard-drawn welded wire fabric to IS 1566
or ACI 318 Reinforcing bars shall
be either Grade Fe 415 or Fe 500, unless specified otherwise.
4.7.2 Welding (including
tack welding)
of reinforcement bars is strictly
prohibited
unless noted.
All reinforcement shall be free from loose mill scales, loose rust and coats of paints, oil, mud or any other substances which may destroy or reduce bond.
All bars shall be bent cold. All bars bending schedules will show bar dimensions as out to out and will consider the bar length as the sum of all detailed dimensions.
Spacers cover blocks and chairs shall be used to maintain the specified nominal cover to the steel reinforcement. Spacers and cover blocks shall
be of concrete of same strength or PVC. Chairs
shall be a minimum
of 8 mm reinforcing steel.
4.8 Steel Reinforcement Binding Wire
Black soft annealed steel binding wire, 16 SWG, shall be used for binding the reinforcing steel at every intersection.
4.9 Formwork for Concrete
4.9.1 Formwork materials shall be straight and
free of warps and any
defects
which would produce
blemishes in exposed concrete and shall conform to IS 14687.
4.9.2 Pre manufactured tube forms shall be of fiber paper, spiral wound and laminated.
4.10 Void Form
Void form shall be of compressible plastic fill materials capable of accommodating swelling of soils. It shall also have
adequate strength to support the loading during
concrete placement.
4.11 TIES
Internal form ties shall be metal, adjustable in length and of a type that no metal will remain within 35mm of the finished concrete surface.
Toes shall have plastic cones at faces of concrete to facilitate patching.
4.12 Chamfer Strips
Chamfer strips shall be 20 to 25 mm, × 45°, cut from extruded PVC or sawn lumber.
4.13 Backfill
4.12.1 Structural fill shall be comprised of clean, well-graded inorganic granular soils.
4.12.2 General engineered fill shall be comprised of clean, well-graded granular soils or inorganic low-plastic cohesive soils.
4.14 Vapour Barrier
Vapor barrier shall be polyethylene sheeting.
4.15 Mastic
Mastic shall be plastic cement, cutback asphalt.
4.16 Anchor bolts
Anchor bolt material shall confirm to IS 1363.
5.0 CONCRETE QUALITY
5.1 Mix Design –
5.1.1 The design of all concrete mixes shall
be by an approved and
certified
laboratory
in the employ
of CONTRACTOR.
5.1.2 The 28 day compressive strength
of concrete shall
be as specified on the drawings. Lean-mix concrete (plain cement concrete) strength shall be 15 MPa. Minimum reinforced concrete strength
shall
be 30 MPa for structural elements.
5.1.3 For pavements and heavy mass construction, the maximum allowable slump shall not exceed 75 mm. The slump shall not exceed 100 mm for all other concrete unless noted on the drawings.
5.1.4 Air entraining
admixtures shall be used
in all concrete
to be exposed to weathering and shall
have
3 to 6 percent
entrained
air by volume.
Concrete for floor slabs whose edges
are exposed to weathering
shall have
3 to 5 percent entrained air by volume
to facilitate the application
of a floor hardener
and sealer as specified on the
drawings.
5.1.5 Mix designs shall be supplied to COMPANY by CONTRACTOR
for acceptance before any concrete is placed.
5.2 Proporting of Concrete Mix
Proportioning of the concrete mix shall be based on the standard deviation computed from compressive
strength tests
of previous batch records or established by laboratory
mix trial.
For a design mix based on the standards deviation computed from compressive strengths of previous batch, the previous batches shall represents similar material and conditions.
In meeting strength requirements, the selected job mix proportions shall provide an average strength FCR, exceeding the
compressive strength FC.
5.3 Sampling, Testing and Quality Assurance
5.3.1 Facilities required for sampling materials, concrete, reinforcement, formwork,
etc. in the field and
in the laboratory shall be provided by the Contractor.
The Contractor shall carry
out all sampling
and
testing in accordance with the relevant India
standards and/or
International
standards
and this
specification. Where no specific
testing
procedure is mentioned,
the tests shall be carried out
as per the prevalent accepted engineering
practice to the directions
of the Engineer. Tests shall be done in the field in the presence of the Engineer or his authorized representative and
at a laboratory company representative approved by the company representative, and the contractor shall submit to the company representative
the test results in triplicate within three days after completion of any
test.
5.3.2 The contractor shall maintain records
of all inspection and testing, which shall be made available
to the company representative. The Engineer at his discretion may waive some
of the stipulations for small unimportant concreting
operations and other works.
5.3.3 Work found unsuitable for acceptance
shall be removed
and replaced
by the Contractor. The work shall be redone
as per specification
requirements and to the satisfaction of the Engineer
at no extra cost to the company.
5.3.4 Quality
Assurance Programme
a) The Contractor shall submit
and finalize a detailed field
Quality Assurance
Programme
within
30 days
from the date of award of the contract, before
commencement of work at
site, according to the
requirements of the specification.
This shall include setting up of a
testing laboratory,
arrangement of testing
apparatus/equipment, deployment of
qualified/experienced
manpower, preparation
of format
for record, field quality plan
etc. On finalized field
quality plan, the Owner shall identify, customer hold points, beyond which work shall not proceed without written approval
from the company
representative. The testing apparatus/equipment installed in the field
laboratory
shall be calibrated /corrected by the authorized
persons as frequently as possible to give
accurate testing results.
b) Frequency of sampling and
testing, etc.
and Assurance
Criteria are given in respective sections. However, the testing frequencies set forth are the desirable minimum
and the company representative
shall have the
full authority
to carry
out or call for tests as
5.4 Failure to meet specification
5.4.1 Batches of concrete not meeting either the slump or air entrainment requirements shall be rejected.
5.4.2 Concrete in place that has not met the requirements of this
specification shall
be removed and
replaced
or repaired as required by COMPANY. Failure to meet specification includes, but is not limited to,
the following:
x Low strength or low
durability
concrete
as evaluated by test results.
x Reinforcement steel size, quantity, strength, position or arrangement not in accordance with drawings or this specification.
x Concrete that differs from the required dimensions or location in such a manner so as to reduce its strength or stability.
x Curing less than specified.
x All costs involved in such work shall be borne by CONTRACTOR.
6.0 PREPARATION FOR PLACING
6.1 Excavation
6.1.1 The excavation shall be of sufficient size to allow for dewatering
and formwork and proper
working space as per the Indian standards. Adequate measures shall be taken to prevent slips, cave-ins
and slides.
6.1.2 Footing excavations shall be carried down to the designated
bearing strata as shown on the drawings.
6.1.3 All foundation excavations and bearing surfaces
shall be inspected by a qualified geotechnical engineer
as required by COMPANY.
6.1.4 Where unsuitable material
is encountered, the
unsuitable
material shall be over excavated
to reach the desired bearing
stratum and backfilled with structural fill
compacted in accordance with site
specific soil report or, alternatively filled
with lean-mix concrete.
6.1.5 If excavations
are carried out below the indicated or specified
elevations due to negligence on the part of the CONTRACTOR,
then the over excavation shall
be refilled to the required elevation with lean
mix concrete
at the CONTRACTOR’s expense.
6.1.6 Excavated
area shall be kept free from loose material, debris and water.
6.1.7 All excavations
and bearing
surfaces shall be protected
against rain,
freezing
temperatures and the ingress
of water at all times during foundation
construction.
6.1.8 If the bearing surface is to be left exposed for more than 24 hours, a 75 mm thick
mat of lean-mix
concrete
shall be placed
on the bearing surface.
6.1.9 Vapor
barrier shall
be placed as shown
on the drawings. Vapor
barrier
shall be lapped 150 mm at joints and shall be sealed with
mastic. Punctures
in vapor barrier shall be sealed with a patch 150
mm larger than puncture
and sealed with mastic.
6.2 Formwork
6.2.1 Formwork shall conform to Indian Standard IS 14687.
6.2.2 Forms
shall be rigidly constructed and
sufficiently tight to prevent leakage.
6.2.3 Panels forming the formwork shall not be dented,
deformed or distorted
from handling or
overuse.
6.2.4 Forms shall be suitable for the particular work. The faces of forms for exposed concrete surfaces shall be selected to provide a smooth surface. Any form surface that comes in contact with concrete shall have mould oil coating, or approved equal.
6.2.5 Forms shall be constructed and assembled to facilitate
their removal without damage to the
concrete.
6.2.6 Forms
shall be left in place for 7 days
or as specified in IS 456
or ACI 318 unless directed
otherwise
by COMPANY. In no case,
shall supporting forms
or shoring be removed until members have acquired 60% of the specified strength to support their weight and imposed loads safely.
6.2.7 Stability and tightness
(at joints) of framework must be maintained during vibration.
6.2.8 Formwork may be constructed from wood,
metal, or any
other elements which assures similar
conditions of efficiency.
6.3 Placing Reinforcement
6.3.1 Placement of reinforcement shall
conform to the
applicable
codes, specifications and recommended practices listed in Section
2.1.
6.3.2 Reinforcement
shall be accurately placed
in accordance with the
drawings. Tolerances
on placement of reinforcement shall
conform to IS 456
or ACI 318 (±10mm for effective
depth
200mm
or less; ± 15mm for effective depth greater than
200mm).
6.3.3 The ends of the black
annealed steel wire used
for binding
the reinforcing material shall not encroach into the concrete cover and
shall be tucked-in to prevent corrosion
spots in the concrete.
6.3.4 Minimum
concrete
clear cover of reinforcement shall
be as specified
on the drawings.
6.3.5 No splices of reinforcement shall be made except as shown. Splices on welded wire fabric shall be made by overlapping two mesh panels.
6.3.6 Exposed reinforcing bars intended for bonding
with future extensions shall be protected
from corrosion by concrete
or other adequate covering.
6.3.7 Welding of reinforcement shall not be allowed without the written acceptance of COMPANY
6.3.8 Wherever conduit, piping, insets, sleeves, etc. as shown on the
drawings interface
with the placing of reinforcement, proper adjustment
shall be made as directed by COMPANY.
6.4 Joints
6.4.1 Construction, control and expansion/isolation joints shall be made in accordance with IS 516 or
ACI
318
6.4.2 Construction
joints not indicated on the drawings shall be made only
with COMPANY's acceptance.
6.4.3 Where a construction joint
is indicated on the drawings, a delay
until the concrete is no longer
plastic
in columns or walls must occur before concrete is placed in the beams, girders,
or slabs to
be supported.
6.4.4 Saw
cuts for control
joints shall be made within 12 hours
after concrete is poured.
6.5 Water Stop
Water spots shall be firmly held in correct position as the concrete is placed. Joints in rubber or plastic water stops shall
be cemented, welded or vulcanized as recommended by the
manufacturer. Joints shall be watertight. Inspection water stops shall be prefabricated and supplied by the same manufacturer,
6.6 Anchor Bolts and Other Embedded Items
Fabrication of anchor bolts and miscellaneous hardware shall be as shown on the drawing and in accordance with applicable codes, specifications and recommended practices listed in section
2 of this specification.
Above all elements shall be held firmly in place through the use of jigs and other approves techniques that avoid movement during the pouring of concrete. All such elements shall be degreased and meticulously cleaned before concrete is poured and expose part shall be properly protected to avoid contact from the poured concrete.
6.7 Inspection
A thorough inspection of the forms, reinforcement and all embedded items shall be made by COMPANY before proceeding with
the placing
of concrete as follow:
a) Reinforcement of correct size and spacing is securely and properly fastened in its correct
position.
b) All forms are correctly located. Structural
strength and
stability
of forms
is Contractor’s responsibility.
c) All embedded items are securely anchored and correctly coated.
d) All forms
and reinforcement
are clean and
wetted as required and excess water and
debris has been
removed form inside
the
forms.
e) Prior to placing concrete, al requirements relating to concrete testing, placement, and finishing as well preparation
for cold or hot weather concreting shall
have been
met and
approved
by COMPANY.
7.0 PRODUCTION, DELIVERY AND PLACEMENT
7.1 Production
7.1.1 Production of concrete shall be in accordance with IS 456 or ACI 318.
7.1.2 Ready-mixed concrete is preferred for jobs where concrete can be placed within
the initial
setting
time after
first mixing of the water, cement and
aggregate.
7.1.3 Concrete shall be mixed only
in batch quantities that can be promptly
disposed of in the work. Concrete shall not be used
after it has acquired
an initial set.
7.1.4 If a site batch plant is used,
COMPANY may require preliminary test batches to ensure concrete quality.
7.1.5 Small quantities of concrete may be site-mixed, providing that
COMPANY's
acceptance of equipment and procedures
to be used
is first obtained.
7.2 Delivery
7.2.1 Concrete will
be conveyed
and handled in accordance with IS 456 or ACI 318.
7.2.2 Concrete must
be delivered and discharged from the truck mixer or agitator truck
within
the initial
setting
time after
introduction
of the water to the cement and aggregate
or the cement to the
aggregate,
unless otherwise accepted by COMPANY.
7.2.3 Retempering is not permitted.
Retempering is defined
as the addition
of water to restore
slump lost during excessive mixing due to excessive
lapse
of time since initial mixing.
7.2.4 Equipment for conveying concrete, such as buckets, trucks,
belt conveyors,
pumps,
etc., shall be of such
design, size and condition to ensure a continuous and adequate supply of concrete of the
specified
mix and slump, without segregation at the
point of deposition.
7.3 Placement
7.3.1 A thorough
inspection of the forms,
reinforcement and all
embedded items shall be made by COMPANY before proceeding with the placing
of concrete as follows:
Reinforcement of correct size and spacing is securely and properly fastened in its correct position.
All forms are correctly located. Structural strength and stability
of forms
is CONTRACTOR’s responsibility.
All embedded items are securely anchored and correctly coated.
All forms and reinforcement are clean and wetted as required, excess water and debris has been
removed from inside the forms.
Inspection by COMPANY does not in any manner relieve CONTRACTOR of his responsibility.
7.3.2 Prior to placing
concrete, all requirements relating
to concrete testing, placement, and
finishing
as well as preparation for cold or hot weather concreting shall
have been
met and approved by COMPANY.
7.3.3 Before placement,
all equipment for delivery and placing shall be cleaned and all
debris,
loose or unsound material, water and
ice removed
from areas to be concreted.
7.3.4 Concrete shall not be placed
against frozen ground
or subgrade, or against soil which has been subject
to excessive water or drying.
7.3.5 The minimum temperature of concrete during placing shall be 10° C. During hot weather, proper attention shall
be given to ingredients, production
methods, handling,
placing,
protection, and curing to prevent excessive
concrete temperatures or water
evaporation that could impair required strength or serviceability of the member or structure. Recommendations
shall conform with IS 7861.
7.3.6 Concrete placement will be such
as to prevent water from collecting at the ends and corners of
the forms and
along form faces.
7.3.7 Concrete shall not be poured during
rain unless adequately protected.
7.3.8 Surface vibrators shall be used. Concrete shall be thoroughly compacted or vibrated. All concrete shall be compacted by internal
vibration
using
mechanical vibrating
equipment, except that concrete
in floor slabs, sidewalks, or curb
and gutter, not poured
against form linings, shall be either tempered or vibrated. Care must be taken in vibrating the concrete to vibrate only
long enough to bring
a continuous film of mortar to the surface.
Vibration shall stop before any
segregation of the concrete occurs. Mechanical vibrators
shall be an approved type as specified
in ACI 309, Chapter 5, IS 2505 or IS 2506. Vibrators shall not be used to spread the concrete.
7.3.9 Install all embedded items such as anchor
bolts, sleeves, inserts,
equipment bed and slide
plates
in their
correct
locations and
secure against displacement.
7.3.10 Concrete shall not be dropped vertically more than 2.5 m; drop chutes shall be used for higher lifts. The chute shall have
a diameter of at least
eight
times the maximum
aggregate size and shall
be positioned
so that the concrete will drop
vertically
7.3.11 In case of placement of ready mix concrete a spare concrete pump shall be made available at all the time
when concreting is in progress.
7.3.12 Ready-mixed concrete is preferred for jobs where concrete can be placed within one and one half
hours after
first mixing of the water, cement and aggregate.
Concrete shall be uniform and thoroughly mixed when delivered to the forms in a freshly mixed and unhardened
state.
No mixing of water in excess of the amount specified for the mix shall be added to the concreting during mixing or hauling
or after the arrival
at the delivery
point.
Concrete may be furnished by ready-mix methods, by volumetric batching and continuous mixing at site, or by batch mixing at site.
a) Ready Mixed Concrete
Ready mixed concrete shall be mixed, transported and placed in a freshly mixed and unhardened
state. The contractor shall furnish the
COMPANY batch record
showing the amount of concrete in cubic
yards,
the time
of loading, the time load
was discharged, and the
type and quantity of each
material including
all admixtures used in each batch of
concrete.
b) Volumetric batching
and continuous mixing at site
Volumetric batching and mixing is normally done at site. The batch and mixing equipment shall conform to the requirements
of ASTM C 685. Concrete made by this method is produced, inspected and documented in conformance with sections 6, 7,8,13
and
14 of ASTM C 685.
c) Batch Mixing at site
This method of batching and mixing is done on site using paving mixers or stationary construction mixers or by using a combination of centrally batching part of the mix and
transporting it to the
site, and adding rest of the material on site.
7.4 Preparation of Forms and Subgrade -
Before placement of concrete, the forma and subgrade shall be free of chips, sawdust, debris, water, ice snow, extraneous
oil, mortar or other harmful
substances
required to be bonded
to the concrete shall
be removed.
Weep holes in walls or slabs shall be formed with nonferrous metal.
7.5 Removal of Forms, Supports and Protective Coatings
Forms, supports and protective coatings shall be removed as practical after the concrete has gained sufficient strength
to support its own weight and superimposed loads. Removal shall
be done so that
the concrete is not damaged and sudden
or excessive stresses are not included.
The accumulated form removal times shall be as per the codes and specifications outlined in section 4 and
this specification.
8.0 CURING AND PROTECTION
8.1 Curing
8.1.1 Curing of concrete shall conform
to IS 456 or ACI 318.
Particular attention shall
be paid to cold and hot weather curing.
8.1.2 During the curing period only such
areas as are needed for immediate surface finish treatment shall be uncovered. After finish treatment,
such areas
shall be immediately re-covered
and the
curing continued.
8.1.3 When the ambient temperature falls
below 5° C, a complete record
of the temperature and the protection given to the
concrete while curing
shall be kept. The number of points at which temperature records are kept shall
be accepted by COMPANY.
8.1.4 Sealing curing
compounds shall not
be used unless specifically
accepted by COMPANY.
They
shall not be used
on vertical
concrete surfaces
which will be exposed
on completion of the job.
8.2 Protection
8.2.1 Protection of concrete shall
conform
to IS 456 or ACI 318.
8.2.2 Freshly placed concrete shall be protected against traffic, direct sunshine, drying
winds, excessive
heat, and cold and rain water.
8.2.3 If grouting
of equipment or base plates is not to be completed
immediately as directed by COMPANY and when
the ambient air temperature is less than 5°C, plastic anchor
bolt sleeves
shall be filled with antifreeze.
9.0 REPAIR AND FINISHING
9.1 Repair
9.1.1 Repair of concrete shall conform to IS 456
or ACI 318.
9.1.2 Repair of voids, honeycombs, sand pockets, excessive finning, and other
similar
gross
imperfections, shall be completed within 24 hours after removal
of forms. Curing procedures shall
not be delayed or interrupted while making such
repairs.
9.1.3 Dry-packed
mortar, consisting of 1 part Portland
cement and 2-1/2 parts of sand
(100 percent
shall pass No. 16 sieve), shall be used to fill
cleaned out voids nominally not exceeding 150 mm in depth or 0.03
cubic meters in volume.
Concrete of the
same mix characteristics
as the concrete to be repaired shall be used to fill larger voids, where a sounder patch can be achieved
than by the use
of dry-pack mortar.
9.1.4 Mortar used in patching shall not be more than one hour old. The mortar patches shall be cured in accordance with this specification. All construction and expansion joints in the completed work shall be left carefully tooled and free of all mortar and concrete. The joint filler shall be left
exposed for its full length with clean and true edges. uniform.
9.2 Finishing
-
The resulting surfaces shall be true and
9.2.1 Finishing
shall conform to IS 456 or ACI 318.
9.2.2 The surfaces
of concrete which are to be grouted shall be left
rough and
unfinished to ensure a
good bond
between concrete and grout.
9.2.3 A smooth-rubbed finish shall
be used on the faces of all exposed concrete unless otherwise specified.
9.2.4 After the final rubbing
is completed
and the surface has dried, it shall be rubbed with burlap to
remove loose powder and shall be left free from
all unsound patches, paste,
powder and objectionable marks.
9.2.5 Sidewalks
and pads shall be given
a broom finish.
9.2.6 Floors shall be given a smooth steel
trowel
finish.
9.2.7 If shown on the
drawings, a colored non-metallic concrete hardener
and sealer
shall be applied
to the floor slabs in strict accordance with the manufacturer's
instructions.
The finished floor slab shall
be in the
color shown on the drawings.
9.3 Concrete in Hot Weather
Concreting in hot weather is performed when high ambient temperatures, high concrete temperature, low relative
humidly etc., are observed.
The contraction shall maintain the temperature of concrete below 90 degrees Fahrenheit
During mixing and conveying
Exposed concrete surfaces that tend to dry or set rapidly will
be continuously moistened.
Using for sprays or any other methods to maintain adequate moisture during the time between placing and finishing of concrete. Water shall not be directly added
to the surface
of concreting
before
finishing.
9.4 Concrete Tolerances
The dimension of formed members, unless otherwise specified will be satisfactory if they conform to the requirement of specifications, the
location shown on the drawings, and are within
the acceptable
tolerances as specified in the codes.
10.0 BACKFILL
Backfill around foundations shall be placed in such a manner as to minimize settlement and to provide a relatively impervious layer to minimize
seepage into the subsoil
and so graded that water does not pond at or close to the foundation.
Backfill shall be general engineered fill and free from organic material, wood scraps, paper or other undesirable material,
Backfill shall not be placed against a concrete foundation until the structure has gained sufficient strength to withstand the earth pressures resulting
from placement and compaction.
Backfill around foundations shall be carefully and uniformly compacted in 150 mm compacted lifts to 95 percent Standard Proctor maximum dry
density at or near
optimum moisture content and shall
consist of clean
material with all lumps broken down
or squeezed together during compaction.
Only hand held compaction equipment shall be used in the compaction of fill within 500 mm of retaining walls.
11.0 CLEAN-UP AND RESTORATION
Upon completion of the work, contractor shall clean up and remove all loose material and debris from
the job site, and dispose of it as waste material as directed by Company.
Before leaving the job site, Contractor shall ensure that all existing structures, roadways and graded areas are returned to a condition satisfactory
to COMPANY and at least equal to that which existed before the work commenced.
12.0 INSPECTION
12.1 CONTRACTOR
shall provide access to the work at all times
to COMPANY
for checking materials, and fabrication and installation procedures.
12.2 Inspection by COMPANY does not in any manner
relive CONTRACTOR of his responsibility.
12.3 COMPANY shall
have the right to stop work and require repairs or alternation
if, in his opinion, the materials or workmanship do not
meet the required specification.
12.4 Any omissions or failure on the
part of the COMPANY
to disapprove or reject any work or materials must not be construed as an acceptance any defective work or materials.
12.5 CONTRACTOR
will bear the cost
of repair and
additional inspection resulting from faulty material or workmanship. .
Civil engineering Hand Book
0 Comments: